Details

    • Type: Task Task
    • Status: Done Done (View Workflow)
    • Priority: Normal Normal
    • Resolution: Unresolved
    • Affects Version/s: UA 4.0.0.6
    • Fix Version/s: None
    • Component/s: UCMDB
    • Labels:
    • Customer:
      Mobinets

      Description

      Click to add description

        Activity

        Taha Arbass made changes -
        Field Original Value New Value
        Gantt Options Milestone (set to milestone: having a due date but zero effort)
        Planned Start 2025-09-26 24:00 (milestone: set planned start date to due date)
        Planned End 2025-09-26 24:00 (milestone: set planned end date to due date)
        Taha Arbass made changes -
        Attachment Screenshot 2025-09-24 162519.png [ 118310 ]
        Taha Arbass made changes -
        Attachment Screenshot 2025-09-24 162557.png [ 118311 ]
        Taha Arbass made changes -
        Attachment Screenshot 2025-09-24 162644.png [ 118312 ]
        Taha Arbass made changes -
        Attachment Screenshot 2025-09-24 162737.png [ 118313 ]
        Taha Arbass made changes -
        Attachment 4.png [ 118314 ]
        Taha Arbass made changes -
        Attachment 4.png [ 118315 ]
        Attachment 5.png [ 118316 ]
        Attachment 6.png [ 118317 ]
        Attachment 7.png [ 118318 ]
        Attachment 8.png [ 118319 ]
        Taha Arbass made changes -
        Attachment 4.png [ 118314 ]
        Taha Arbass made changes -
        Status To Do [ 10001 ] Done [ 10000 ]
        Taha Arbass made changes -
        Assignee Taha Arbass [ tarbass ] Bessem Manita [ bmanita ]
        Taha Arbass made changes -
        Assignee Bessem Manita [ bmanita ] Taha Arbass [ tarbass ]
        Taha Arbass made changes -
        Status Done [ 10000 ] To Do [ 10001 ]
        Taha Arbass made changes -
        Attachment Screenshot 2025-09-24 162737.png [ 118313 ]
        Taha Arbass made changes -
        Attachment Screenshot 2025-09-24 162644.png [ 118312 ]
        Taha Arbass made changes -
        Attachment 4.png [ 118315 ]
        Taha Arbass made changes -
        Attachment 5.png [ 118316 ]
        Taha Arbass made changes -
        Attachment 6.png [ 118317 ]
        Taha Arbass made changes -
        Attachment 7.png [ 118318 ]
        Taha Arbass made changes -
        Attachment 8.png [ 118319 ]
        Taha Arbass made changes -
        Attachment Screenshot 2025-09-24 162519.png [ 118310 ]
        Taha Arbass made changes -
        Attachment Screenshot 2025-09-24 162557.png [ 118311 ]
        Taha Arbass made changes -
        Status To Do [ 10001 ] In Progress [ 3 ]
        Taha Arbass made changes -
        Remaining Estimate 0 minutes [ 0 ]
        Time Spent 7 hours, 30 minutes [ 27000 ]
        Worklog Id 278571 [ 278571 ]
        Taha Arbass made changes -
        Baseline Start 2025-09-26 24:00 (set baseline based of initial work logging)
        Baseline End 2025-09-26 24:00 (set baseline based of initial work logging)
        Taha Arbass made changes -
        Time Spent 7 hours, 30 minutes [ 27000 ] 1 day, 6 hours, 30 minutes [ 52200 ]
        Worklog Id 278663 [ 278663 ]
        Taha Arbass made changes -
        Remaining Estimate 0 minutes [ 0 ] 1 day [ 28800 ]
        Time Spent 1 day, 6 hours, 30 minutes [ 52200 ] 2 days, 6 hours, 30 minutes [ 81000 ]
        Worklog Id 278900 [ 278900 ]
        Taha Arbass made changes -
        Remaining Estimate 1 day [ 28800 ] 3 hours [ 10800 ]
        Time Spent 2 days, 6 hours, 30 minutes [ 81000 ] 3 days, 6 hours, 30 minutes [ 109800 ]
        Worklog Id 279037 [ 279037 ]
        Taha Arbass made changes -
        Status In Progress [ 3 ] Done [ 10000 ]
        Taha Arbass made changes -
        Assignee Taha Arbass [ tarbass ] Bessem Manita [ bmanita ]
        Taha Arbass made changes -
        Due Date 26/Sep/25 01/Oct/25
        Taha Arbass made changes -
        Planned End 2025-09-26 24:00 2025-10-01 24:00 (auto-generated by shift of due date)
        Taha Arbass made changes -
        Remaining Estimate 3 hours [ 10800 ] 0 minutes [ 0 ]
        Time Spent 3 days, 6 hours, 30 minutes [ 109800 ] 4 days, 6 hours, 30 minutes [ 138600 ]
        Worklog Id 279174 [ 279174 ]
        Bessem Manita made changes -
        Status Done [ 10000 ] In Progress [ 3 ]
        Bessem Manita made changes -
        Assignee Bessem Manita [ bmanita ] Thierno Bah [ tbah ]
        Thierno Bah made changes -
        Thierno Bah made changes -
        Thierno Bah made changes -
        Time Spent 4 days, 6 hours, 30 minutes [ 138600 ] 1 week, 30 minutes [ 145800 ]
        Worklog Id 285628 [ 285628 ]
        Thierno Bah made changes -
        Thierno Bah made changes -
        Status In Progress [ 3 ] Done [ 10000 ]
        Thierno Bah made changes -
        Time Spent 1 week, 30 minutes [ 145800 ] 1 week, 5 hours, 30 minutes [ 163800 ]
        Worklog Id 286065 [ 286065 ]

          People

          • Assignee:
            Thierno Bah
            Reporter:
            Bessem Manita
          • Votes:
            0 Vote for this issue
            Watchers:
            2 Start watching this issue

            Dates

            • Due:
              Created:
              Updated:
              Planned Start:
              Planned End:
              Actual Start:
              Date of Baselining:

              Time Tracking

              Estimated:
              Original Estimate - Not Specified
              Not Specified
              Remaining:
              Remaining Estimate - 0 minutes
              0m
              Logged:
              Time Spent - 1 week, 5 hours, 30 minutes
              1w 5h 30m

                Drag and Drop