Details

    • Type: Task Task
    • Status: Done Done (View Workflow)
    • Priority: Normal Normal
    • Resolution: Unresolved
    • Affects Version/s: None
    • Fix Version/s: None
    • Component/s: FN, SRD
    • Labels:
      None Labels
    • Customer:
      OMAN-Tel

      Description

      Click to add description

        Activity

        zTrabelsi made changes -
        Field Original Value New Value
        Gantt Options Milestone (set to milestone: having a due date but zero effort)
        Planned Start 2025-09-24 24:00 (milestone: set planned start date to due date)
        Planned End 2025-09-24 24:00 (milestone: set planned end date to due date)
        Zein Trabelsi made changes -
        Assignee Zein Trabelsi [ ztrabelsi ]
        Zein Trabelsi made changes -
        Status To Do [ 10001 ] In Progress [ 3 ]
        Zein Trabelsi made changes -
        Remaining Estimate 0 minutes [ 0 ]
        Time Spent 1 day [ 28800 ]
        Worklog Id 278649 [ 278649 ]
        zTrabelsi made changes -
        Baseline Start 2025-09-24 24:00 (set baseline based of initial work logging)
        Baseline End 2025-09-24 24:00 (set baseline based of initial work logging)
        Zein Trabelsi made changes -
        Time Spent 1 day [ 28800 ] 2 days [ 57600 ]
        Worklog Id 278650 [ 278650 ]
        Khaled Khalil made changes -
        Component/s FN [ 16303 ]
        Component/s SRD [ 16304 ]
        Zein Trabelsi made changes -
        Time Spent 2 days [ 57600 ] 3 days [ 86400 ]
        Worklog Id 279200 [ 279200 ]
        Zein Trabelsi made changes -
        Time Spent 3 days [ 86400 ] 3 days, 2 hours [ 93600 ]
        Worklog Id 281875 [ 281875 ]
        Zein Trabelsi made changes -
        Time Spent 3 days, 2 hours [ 93600 ] 4 days, 2 hours [ 122400 ]
        Worklog Id 282152 [ 282152 ]
        Zein Trabelsi made changes -
        Time Spent 4 days, 2 hours [ 122400 ] 1 week, 2 hours [ 151200 ]
        Worklog Id 282155 [ 282155 ]
        Zein Trabelsi made changes -
        Time Spent 1 week, 2 hours [ 151200 ] 1 week, 1 day, 2 hours [ 180000 ]
        Worklog Id 282157 [ 282157 ]
        Zein Trabelsi made changes -
        Status In Progress [ 3 ] Done [ 10000 ]

          People

          • Assignee:
            Zein Trabelsi
            Reporter:
            Zein Trabelsi
          • Votes:
            0 Vote for this issue
            Watchers:
            1 Start watching this issue

            Dates

            • Due:
              Created:
              Updated:
              Planned Start:
              Planned End:
              Actual Start:
              Date of Baselining:

              Time Tracking

              Estimated:
              Original Estimate - Not Specified
              Not Specified
              Remaining:
              Remaining Estimate - 0 minutes
              0m
              Logged:
              Time Spent - 1 week, 1 day, 2 hours
              1w 1d 2h

                Drag and Drop