Details
-
Type:
Bug
-
Status:
Ready for QA
(View Workflow)
-
Priority:
Normal
-
Resolution: Unresolved
-
Affects Version/s: None
-
Fix Version/s: None
-
Component/s: UCMDB
-
Labels:None Labels
-
Customer:Mobinets
Description
When trying to edit a OSP pathway this message is displayed:
The page you are looking for does not exist.
Attachments
Activity
| Field | Original Value | New Value |
|---|---|---|
| Gantt Options | Milestone (set to milestone: having a due date but zero effort) | |
| Planned Start | 2025-12-30 24:00 (milestone: set planned start date to due date) | |
| Planned End | 2025-12-30 24:00 (milestone: set planned end date to due date) |
| Project | ACE_Omantel_Migration [ 14500 ] | ACE [ 14100 ] |
| Key | ACEOPSHIFT-153 | ACE-293 |
| Issue Type | New Feature [ 2 ] | Bug [ 1 ] |
| Workflow | ACEOPSHIFT: Simple Issue Tracking Workflow [ 197401 ] | Mobinets_Dev_BugWF_J4.4 [ 198008 ] |
| Status | To Do [ 10001 ] | Open Bug [ 10108 ] |
| Assignee | Khaled Khalil [ kkhalil ] |
| Component/s | UCMDB [ 16302 ] |
| Assignee | Khaled Khalil [ kkhalil ] | Bessem Manita [ bmanita ] |
| Customer | OMAN-Tel [ 12200 ] | Mobinets [ 12900 ] |
| Assignee | Bessem Manita [ bmanita ] | Thierno Bah [ tbah ] |
| Status | Open Bug [ 10108 ] | Dev Scheduled [ 10014 ] |
| Status | Dev Scheduled [ 10014 ] | Implementation in progress [ 10016 ] |
| Attachment | Capture d'écran 2025-11-10 152650.png [ 121612 ] |
| Assignee | Thierno Bah [ tbah ] | amer bdeoui [ abdeoui ] |
| Remaining Estimate | 0 minutes [ 0 ] | |
| Time Spent | 1 hour, 30 minutes [ 5400 ] | |
| Worklog Id | 282983 [ 282983 ] |
| Baseline Start | 2025-12-30 24:00 (set baseline based of initial work logging) | |
| Baseline End | 2025-12-30 24:00 (set baseline based of initial work logging) |
| Status | Implementation in progress [ 10016 ] | To Be Released [ 10400 ] |