Description
When creating an FO cable, we need to attach the cable to a pathway.
When clicking on OSP pathways menu, no pathway is shown and the creation cannot be made.
Attachments
Activity
| Field | Original Value | New Value |
|---|---|---|
| Gantt Options | Milestone (set to milestone: having a due date but zero effort) | |
| Planned Start | 2025-12-31 24:00 (milestone: set planned start date to due date) | |
| Planned End | 2025-12-31 24:00 (milestone: set planned end date to due date) |
| Assignee | Hassan Abdine [ habdine ] | Thierno Bah [ tbah ] |
| Remaining Estimate | 0 minutes [ 0 ] | |
| Time Spent | 1 hour, 18 minutes [ 4680 ] | |
| Worklog Id | 284735 [ 284735 ] |
| Baseline Start | 2025-12-31 24:00 (set baseline based of initial work logging) | |
| Baseline End | 2025-12-31 24:00 (set baseline based of initial work logging) |
| Status | Open Bug [ 10108 ] | Dev Scheduled [ 10014 ] |
| Status | Dev Scheduled [ 10014 ] | Implementation in progress [ 10016 ] |
| Attachment | Capture d'écran 2025-11-28 152434.png [ 123010 ] | |
| Attachment | Capture d'écran 2025-11-28 152536.png [ 123011 ] | |
| Attachment | Capture d'écran 2025-11-28 152550.png [ 123012 ] | |
| Attachment | Capture d'écran 2025-11-28 152606.png [ 123013 ] | |
| Attachment | Capture d'écran 2025-11-28 152623.png [ 123014 ] |
| Status | Implementation in progress [ 10016 ] | To Be Released [ 10400 ] |
| Status | To Be Released [ 10400 ] | Ready for QA [ 10023 ] |
| Assignee | Thierno Bah [ tbah ] | amer bdeoui [ abdeoui ] |
| Time Spent | 1 hour, 18 minutes [ 4680 ] | 7 hours, 48 minutes [ 28080 ] |
| Worklog Id | 284875 [ 284875 ] |