fn:getPeNeDetailsContext/getAccessNeDetailsContext/getAccessDeviceDetails/getPossibleOspConnections/getTransferedOspConnectionsByNode1OrNode2/

    Details

    • Type: Task Task
    • Status: Done Done (View Workflow)
    • Priority: Normal Normal
    • Resolution: Unresolved
    • Affects Version/s: None
    • Fix Version/s: None
    • Component/s: UCMDB
    • Labels:
      None Labels
    • Customer:
      Mobinets

      Description

      Click to add description

        Activity

        Subversion JIRA

        Links Hierarchy

         Documentation

        Invalid license: EXPIRED

        Transition Time In Source Status Execution Times Last Executer Last Execution Date
        To Do To Do Done Done
        9d 7h 33m 1 Nouha Mhadhbi 12/Dec/25 1:54 PM
        Nouha Mhadhbi made changes -
        Status To Do [ 10001 ] Done [ 10000 ]
        Hide
        Nouha Mhadhbi added a comment -

        finished

        Show
        Nouha Mhadhbi added a comment - finished
        Nouha Mhadhbi made changes -
        Baseline Start 2025-12-03 24:00 (set baseline based of initial work logging)
        Baseline End 2025-12-03 24:00 (set baseline based of initial work logging)
        Nouha Mhadhbi made changes -
        Remaining Estimate 0 minutes [ 0 ]
        Time Spent 7 hours [ 25200 ]
        Worklog Id 285981 [ 285981 ]
        made changes -
        Summary fn:getAccessDeviceDetails/getPossibleOspConnections/getTransferedOspConnectionsByNode1OrNode2 fn:getPeNeDetailsContext/getAccessNeDetailsContext/getAccessDeviceDetails/getPossibleOspConnections/getTransferedOspConnectionsByNode1OrNode2/
        made changes -
        Summary fn fn:getAccessDeviceDetails/getPossibleOspConnections/getTransferedOspConnectionsByNode1OrNode2
        Khaled Khalil made changes -
        Component/s UCMDB [ 16302 ]
        Nouha Mhadhbi made changes -
        Field Original Value New Value
        Gantt Options Milestone (set to milestone: having a due date but zero effort)
        Planned Start 2025-12-03 24:00 (milestone: set planned start date to due date)
        Planned End 2025-12-03 24:00 (milestone: set planned end date to due date)
        Nouha Mhadhbi logged work - 03/Dec/25 12:00 AM
        • Time Spent:
          7 hours
           

          finished

          People

          • Assignee:
            Nouha Mhadhbi
            Reporter:
            Nouha Mhadhbi
          • Votes:
            0 Vote for this issue
            Watchers:
            1 Start watching this issue

            Dates

            • Due:
              Created:
              Updated:
              Planned Start:
              Planned End:
              Actual Start:
              Date of Baselining:

              Time Tracking

              Estimated:
              Original Estimate - Not Specified
              Not Specified
              Remaining:
              Remaining Estimate - 0 minutes
              0m
              Logged:
              Time Spent - 7 hours
              7h

                Drag and Drop