Details
-
Type:
Bug
-
Status:
Closed
(View Workflow)
-
Priority:
Normal
-
Resolution: Cancelled
-
Affects Version/s: None
-
Fix Version/s: None
-
Component/s: UCMDB
-
Labels:None Labels
-
Customer:OMAN-Tel
Description
ACE, on GIS view, tried to select a site on the map so that it is highlighted in the navigation window, but I am unable to select a site.
Attachments
Activity
| Status | Reopened [ 4 ] | Closed [ 6 ] |
| Resolution | Not Fixed [ 10200 ] | Cancelled [ 10100 ] |
| Assignee | Eyob Tatek [ etatek ] | Bessem Manita [ bmanita ] |
| Resolution | Cancelled [ 10100 ] | Not Fixed [ 10200 ] |
| Status | Rejected [ 10100 ] | Reopened [ 4 ] |
| Attachment | site_select.png [ 124816 ] |
| Status | Open Bug [ 10108 ] | Rejected [ 10100 ] |
| Assignee | Omar Kamalddine [ okamalddine ] | Eyob Tatek [ etatek ] |
| Resolution | Cancelled [ 10100 ] |
made changes -
| Description |
ACE, on GIS view, tried to select a site on the map so that it is highlighted in the navigation window, but I am unable to select a site. Site is also not available in the navigation window.
Platform http://10.172.20.88:6016/ACE_UCMDB_UI/ |
ACE, on GIS view, tried to select a site on the map so that it is highlighted in the navigation window, but I am unable to select a site.
Platform http://10.172.20.88:6016/ACE_UCMDB_UI/ |
| Assignee | Khaled Khalil [ kkhalil ] | Omar Kamalddine [ okamalddine ] |
| Component/s | UCMDB [ 16302 ] |
| Assignee | Hassan Abdine [ habdine ] | Khaled Khalil [ kkhalil ] |
| Field | Original Value | New Value |
|---|---|---|
| Gantt Options | Milestone (set to milestone: having a due date but zero effort) | |
| Planned Start | 2025-12-31 24:00 (milestone: set planned start date to due date) | |
| Planned End | 2025-12-31 24:00 (milestone: set planned end date to due date) |