1-update ServiceInterfaceClientCsvHandler file BE
2-add EthernetTrunkCsvImportContainer UI
3-add EthernetTrunkPage UI
4-update parent layout of EthernetTrunkViewContainer to EthernetTrunkPage
5-add import btn to addImportCsvButton
6-test with file in attachement
Attachments
Activity
| Field | Original Value | New Value |
|---|---|---|
| Gantt Options | Milestone (set to milestone: having a due date but zero effort) | |
| Planned Start | 2025-12-18 24:00 (milestone: set planned start date to due date) | |
| Planned End | 2025-12-18 24:00 (milestone: set planned end date to due date) |
| Status | To Do [ 10001 ] | In Progress [ 3 ] |
| Description |
1-update ServiceInterfaceClientCsvHandler file BE
2-add EthernetTrunkCsvImportContainer UI 3-add EthernetTrunkPage UI 4-update parent layout of EthernetTrunkViewContainer to EthernetTrunkPage 5-add import btn to addImportCsvButton 6-test with file in attachement |
| Attachment | testTrunk.csv [ 124406 ] |
| Remaining Estimate | 0 minutes [ 0 ] | |
| Time Spent | 1 hour, 30 minutes [ 5400 ] | |
| Worklog Id | 286407 [ 286407 ] |
| Baseline Start | 2025-12-18 24:00 (set baseline based of initial work logging) | |
| Baseline End | 2025-12-18 24:00 (set baseline based of initial work logging) |
| Status | In Progress [ 3 ] | Done [ 10000 ] |
| Time Spent | 1 hour, 30 minutes [ 5400 ] | 3 hours, 30 minutes [ 12600 ] |