Details

    • Type: Task Task
    • Status: Done Done (View Workflow)
    • Priority: Normal Normal
    • Resolution: Unresolved
    • Affects Version/s: None
    • Fix Version/s: None
    • Component/s: UCMDB
    • Labels:
      None Labels
    • Customer:
      Mobinets

      Description

      Click to add description

        Activity

        Tayeb Gasmi made changes -
        Field Original Value New Value
        Gantt Options Milestone (set to milestone: having a due date but zero effort)
        Planned Start 2026-01-13 24:00 (milestone: set planned start date to due date)
        Planned End 2026-01-13 24:00 (milestone: set planned end date to due date)
        Khaled Khalil made changes -
        Assignee Tayeb Gasmi [ tgasmi ]
        Tayeb Gasmi logged work - 16/Jan/26 12:00 AM
        • Time Spent:
          1 day
           

          Create new service using exiting lambda

        Tayeb Gasmi made changes -
        Status To Do [ 10001 ] In Progress [ 3 ]
        Tayeb Gasmi logged work - 19/Jan/26 12:00 AM
        • Time Spent:
          1 day
           

          Create new service using exiting lambda

        Tayeb Gasmi logged work - 20/Jan/26 12:00 AM
        • Time Spent:
          1 day
           

          Create new service using exiting lambda

        Tayeb Gasmi logged work - 21/Jan/26 12:00 AM
        • Time Spent:
          1 day
           

          Create new service using exiting lambda

        Tayeb Gasmi made changes -
        Remaining Estimate 0 minutes [ 0 ]
        Time Spent 1 day [ 28800 ]
        Worklog Id 289431 [ 289431 ]
        Tayeb Gasmi made changes -
        Baseline Start 2026-01-13 24:00 (set baseline based of initial work logging)
        Baseline End 2026-01-13 24:00 (set baseline based of initial work logging)
        Tayeb Gasmi made changes -
        Time Spent 1 day [ 28800 ] 2 days [ 57600 ]
        Worklog Id 289432 [ 289432 ]
        Tayeb Gasmi made changes -
        Time Spent 2 days [ 57600 ] 3 days [ 86400 ]
        Worklog Id 289536 [ 289536 ]
        Tayeb Gasmi made changes -
        Time Spent 3 days [ 86400 ] 4 days [ 115200 ]
        Worklog Id 289537 [ 289537 ]
        Tayeb Gasmi made changes -
        Status In Progress [ 3 ] Done [ 10000 ]
        Hide
        Tayeb Gasmi added a comment -

        done

        Show
        Tayeb Gasmi added a comment - done
        Transition Time In Source Status Execution Times Last Executer Last Execution Date
        To Do To Do In Progress In Progress
        2d 20h 46m 1 Tayeb Gasmi 16/Jan/26 8:31 AM
        In Progress In Progress Done Done
        11d 1h 47m 1 Tayeb Gasmi 27/Jan/26 10:18 AM
        Subversion JIRA

        Links Hierarchy

         Documentation

        Invalid license: EXPIRED

          People

          • Assignee:
            Tayeb Gasmi
            Reporter:
            Tayeb Gasmi
          • Votes:
            0 Vote for this issue
            Watchers:
            1 Start watching this issue

            Dates

            • Due:
              Created:
              Updated:
              Planned Start:
              Planned End:
              Actual Start:
              Date of Baselining:

              Time Tracking

              Estimated:
              Original Estimate - Not Specified
              Not Specified
              Remaining:
              Remaining Estimate - 0 minutes
              0m
              Logged:
              Time Spent - 4 days
              4d

                Drag and Drop