        Mohamad Ghorghar logged work - 23/Jan/26 12:00 AM
        • Time Spent:
          1 day
           

          The Device management was implemented and tested for these network elements : BTS, NodeB, eNodeB, BSC, SGW, RNC, MSC

        Mohamad Ghorghar made changes -
        Field Original Value New Value
        Epic Link NEPX-14495 [ 123331 ]
        Mohamad Ghorghar made changes -
        Gantt Options Milestone (set to milestone: having a due date but zero effort)
        Planned Start 2026-01-27 24:00 (milestone: set planned start date to due date)
        Planned End 2026-01-27 24:00 (milestone: set planned end date to due date)
        Hide
        Mohamad Ghorghar added a comment -

        The Device management was implemented and tested for these network elements : BTS, NodeB, eNodeB, BSC, SGW, RNC, MSC

        Show
        Mohamad Ghorghar added a comment - The Device management was implemented and tested for these network elements : BTS, NodeB, eNodeB, BSC, SGW, RNC, MSC
        Mohamad Ghorghar made changes -
        Remaining Estimate 0 minutes [ 0 ]
        Time Spent 1 day [ 28800 ]
        Worklog Id 289553 [ 289553 ]
        Mohamad Ghorghar made changes -
        Baseline Start 2026-01-27 24:00 (set baseline based of initial work logging)
        Baseline End 2026-01-27 24:00 (set baseline based of initial work logging)
        Mohamad Ghorghar made changes -
        Status To Do [ 10001 ] In Progress [ 3 ]
        Mohamad Ghorghar logged work - 26/Jan/26 12:00 AM
        • Time Spent:
          1 day
           

          The Device management was implemented and tested for these network elements : sgsn,sranbs,srancontroller,trau,ggsn,hlr,hss,ipclk,mfs

        Mohamad Ghorghar logged work - 27/Jan/26 12:00 AM
        • Time Spent:
          1 day
           

          Refactored the save function to match old NEP logic + did casting there was a mismatch betwwen the entity and SQL

        Hide
        Mohamad Ghorghar added a comment -

        The Device management was implemented and tested for these network elements : sgsn,sranbs,srancontroller,trau,ggsn,hlr,hss,ipclk,mfs

        Show
        Mohamad Ghorghar added a comment - The Device management was implemented and tested for these network elements : sgsn,sranbs,srancontroller,trau,ggsn,hlr,hss,ipclk,mfs
        Mohamad Ghorghar made changes -
        Time Spent 1 day [ 28800 ] 2 days [ 57600 ]
        Worklog Id 289712 [ 289712 ]
        Mohamad Ghorghar made changes -
        Time Spent 2 days [ 57600 ] 3 days [ 86400 ]
        Worklog Id 289955 [ 289955 ]
        Hide
        Mohamad Ghorghar added a comment -

        Refactored the save function to match old NEP logic + did casting there was a mismatch betwwen the entity and SQL

        Show
        Mohamad Ghorghar added a comment - Refactored the save function to match old NEP logic + did casting there was a mismatch betwwen the entity and SQL
        Mohamad Ghorghar made changes -
        Attachment Screenshot 2026-01-28 115143.jpg [ 127113 ]
        Attachment Screenshot 2026-01-28 115241.jpg [ 127114 ]
        Mohamad Ghorghar made changes -
        Status In Progress [ 3 ] Done [ 10000 ]
        Transition Time In Source Status Execution Times Last Executer Last Execution Date
        To Do To Do In Progress In Progress
        7h 52m 1 Mohamad Ghorghar 23/Jan/26 2:41 PM
        In Progress In Progress Done Done
        4d 18h 32m 1 Mohamad Ghorghar 28/Jan/26 9:13 AM
        Subversion JIRA

        Links Hierarchy

         Documentation

        Invalid license: EXPIRED

          People

          • Assignee:
            Mohamad Ghorghar
            Reporter:
            Mohamad Ghorghar
          • Votes:
            0 Vote for this issue
            Watchers:
            1 Start watching this issue

            Dates

            • Due:
              Created:
              Updated:
              Planned Start:
              Planned End:
              Actual Start:
              Date of Baselining:

              Time Tracking

              Estimated:
              Original Estimate - Not Specified
              Not Specified
              Remaining:
              Remaining Estimate - 0 minutes
              0m
              Logged:
              Time Spent - 3 days
              3d

                Drag and Drop