Route Builder reports - Integrate RB reports for all nodes : BTS, NodeB, ENODEB, GNODEB,RNC,CoreElement,BSC ...
Activity
| Field | Original Value | New Value |
|---|---|---|
| Gantt Options | Milestone (set to milestone: having a due date but zero effort) | |
| Planned Start | 2026-02-27 24:00 (milestone: set planned start date to due date) | |
| Planned End | 2026-02-27 24:00 (milestone: set planned end date to due date) |
| Assignee | Tayeb Gasmi [ tgasmi ] |
-
- Time Spent:
- 1 day
-
Route Builder reports - Integrate RB reports for all nodes
| Status | To Do [ 10001 ] | Done [ 10000 ] |
-
- Time Spent:
- 1 day
-
integrate rb reports for all nodes
-
- Time Spent:
- 1 day
-
integrate rb routes for all nodes
| Remaining Estimate | 0 minutes [ 0 ] | |
| Time Spent | 1 day [ 28800 ] | |
| Worklog Id | 299811 [ 299811 ] |
| Baseline Start | 2026-02-27 24:00 (set baseline based of initial work logging) | |
| Baseline End | 2026-02-27 24:00 (set baseline based of initial work logging) |
| Time Spent | 1 day [ 28800 ] | 2 days [ 57600 ] |
| Worklog Id | 299813 [ 299813 ] |
| Time Spent | 2 days [ 57600 ] | 3 days [ 86400 ] |
| Worklog Id | 299832 [ 299832 ] |
| Time Spent | 3 days [ 86400 ] | 4 days [ 115200 ] |
| Worklog Id | 299833 [ 299833 ] |
| Remaining Estimate | 0 minutes [ 0 ] | 1 day [ 28800 ] |
| Time Spent | 4 days [ 115200 ] | 3 days [ 86400 ] |
| Worklog Id | 299811 [ 299811 ] | |
| Worklog Time Spent | 1 day [ 28800 ] |
| Transition | Time In Source Status | Execution Times | Last Executer | Last Execution Date | |||||
|---|---|---|---|---|---|---|---|---|---|
|
111d 15h 11m | 1 | Tayeb Gasmi | 15/May/26 7:34 AM |
|