Details

    • Type: Task Task
    • Status: Done Done (View Workflow)
    • Priority: Normal Normal
    • Resolution: Unresolved
    • Affects Version/s: UCMDB 4.0.0.17
    • Fix Version/s: None
    • Component/s: UCMDB
    • Labels:

      Description

      Click to add description

        Activity

        Tayeb Gasmi made changes -
        Field Original Value New Value
        Epic Link NEPX-14495 [ 123331 ]
        Tayeb Gasmi made changes -
        Gantt Options Milestone (set to milestone: having a due date but zero effort)
        Planned Start 2026-02-06 24:00 (milestone: set planned start date to due date)
        Planned End 2026-02-06 24:00 (milestone: set planned end date to due date)
        Tayeb Gasmi made changes -
        Labels UCMDB_WEB
        Khaled Khalil made changes -
        Summary failure impact anlysais failure impact anlysis
        Bessem Manita made changes -
        Summary failure impact anlysis failure impact analysis
        Tayeb Gasmi made changes -
        Summary failure impact analysis failure impact anlysais
        Tayeb Gasmi made changes -
        Status To Do [ 10001 ] In Progress [ 3 ]
        Tayeb Gasmi made changes -
        Remaining Estimate 0 minutes [ 0 ]
        Time Spent 1 day [ 28800 ]
        Worklog Id 291028 [ 291028 ]
        Tayeb Gasmi made changes -
        Baseline Start 2026-02-06 24:00 (set baseline based of initial work logging)
        Baseline End 2026-02-06 24:00 (set baseline based of initial work logging)
        Tayeb Gasmi made changes -
        Time Spent 1 day [ 28800 ] 2 days [ 57600 ]
        Worklog Id 291034 [ 291034 ]
        Tayeb Gasmi made changes -
        Time Spent 2 days [ 57600 ] 3 days [ 86400 ]
        Worklog Id 291035 [ 291035 ]
        Tayeb Gasmi made changes -
        Time Spent 3 days [ 86400 ] 4 days [ 115200 ]
        Worklog Id 291036 [ 291036 ]
        Tayeb Gasmi made changes -
        Remaining Estimate 0 minutes [ 0 ] 1 day [ 28800 ]
        Time Spent 4 days [ 115200 ] 3 days [ 86400 ]
        Worklog Id 291028 [ 291028 ]
        Worklog Time Spent 1 day [ 28800 ]
        Tayeb Gasmi made changes -
        Status In Progress [ 3 ] Done [ 10000 ]
        Tayeb Gasmi made changes -
        Remaining Estimate 1 day [ 28800 ] 0 minutes [ 0 ]
        Time Spent 3 days [ 86400 ] 4 days [ 115200 ]
        Worklog Id 291241 [ 291241 ]

          People

          • Assignee:
            Tayeb Gasmi
            Reporter:
            Tayeb Gasmi
          • Votes:
            0 Vote for this issue
            Watchers:
            1 Start watching this issue

            Dates

            • Due:
              Created:
              Updated:
              Planned Start:
              Planned End:
              Actual Start:
              Date of Baselining:

              Time Tracking

              Estimated:
              Original Estimate - Not Specified
              Not Specified
              Remaining:
              Remaining Estimate - 0 minutes
              0m
              Logged:
              Time Spent - 4 days
              4d

                Drag and Drop