Details

    • Type: Task Task
    • Status: Done Done (View Workflow)
    • Priority: Normal Normal
    • Resolution: Unresolved
    • Affects Version/s: None
    • Fix Version/s: None
    • Component/s: UCMDB
    • Labels:

      Description

      The 4G Cells edit form needs to be reviewed and aligned with the NEP Cells edit form.

      Several fields that exist in the NEP Cells edit form are currently missing in the 4G Cells edit form.

        Activity

        Bessem Manita made changes -
        Field Original Value New Value
        Epic Link NEPX-14495 [ 123331 ]
        Bessem Manita made changes -
        Gantt Options Milestone (set to milestone: having a due date but zero effort)
        Planned Start 2026-03-06 24:00 (milestone: set planned start date to due date)
        Planned End 2026-03-06 24:00 (milestone: set planned end date to due date)
        Khaled Khalil made changes -
        Assignee Bessem Manita [ bmanita ] Abdel Rahman Tout [ atout ]
        Abdel Rahman Tout logged work - 31/Mar/26 12:00 AM
        • Time Spent:
          1 day
           

          FIxed the route of the new case.
          continue working on the implementation of view
          Fixed the save finction
          Trying to test it and testing the generic code.

        Abdel Rahman Tout made changes -
        Remaining Estimate 0 minutes [ 0 ]
        Time Spent 1 day [ 28800 ]
        Worklog Id 295756 [ 295756 ]
        Abdel Rahman Tout made changes -
        Baseline Start 2026-03-06 24:00 (set baseline based of initial work logging)
        Baseline End 2026-03-06 24:00 (set baseline based of initial work logging)
        Abdel Rahman Tout logged work - 01/Apr/26 12:00 AM
        • Time Spent:
          1 day
           

          Finished the task.

        Abdel Rahman Tout made changes -
        Time Spent 1 day [ 28800 ] 2 days [ 57600 ]
        Worklog Id 295848 [ 295848 ]
        Abdel Rahman Tout logged work - 02/Apr/26 12:00 AM
        • Time Spent:
          1 day
           

          Updating on the generic case.

        Abdel Rahman Tout made changes -
        Status To Do [ 10001 ] Done [ 10000 ]
        Abdel Rahman Tout made changes -
        Time Spent 2 days [ 57600 ] 3 days [ 86400 ]
        Worklog Id 295912 [ 295912 ]
        Abdel Rahman Tout logged work - 03/Apr/26 12:00 AM
        • Time Spent:
          6 hours
           

          Trying to add a local code instead of the generic.
          Fixed the issue related to the word in the Catalog project.

        Abdel Rahman Tout made changes -
        Time Spent 3 days [ 86400 ] 3 days, 6 hours [ 108000 ]
        Worklog Id 296030 [ 296030 ]
        Transition Time In Source Status Execution Times Last Executer Last Execution Date
        To Do To Do Done Done
        28d 22h 10m 1 Abdel Rahman Tout 02/Apr/26 5:40 AM
        Subversion JIRA

        Links Hierarchy

         Documentation

        Invalid license: EXPIRED

          People

          • Assignee:
            Abdel Rahman Tout
            Reporter:
            Bessem Manita
          • Votes:
            0 Vote for this issue
            Watchers:
            1 Start watching this issue

            Dates

            • Due:
              Created:
              Updated:
              Planned Start:
              Planned End:
              Actual Start:
              Date of Baselining:

              Time Tracking

              Estimated:
              Original Estimate - Not Specified
              Not Specified
              Remaining:
              Remaining Estimate - 0 minutes
              0m
              Logged:
              Time Spent - 3 days, 6 hours
              3d 6h

                Drag and Drop