Details

    • Type: Bug Bug
    • Status: Ready for QA Ready for QA (View Workflow)
    • Priority: Normal Normal
    • Resolution: Not Fixed
    • Affects Version/s: None
    • Fix Version/s: None
    • Component/s: UCMDB
    • Labels:
    • Customer:
      Mobinets

      Description

      Platform: http://65.108.79187:6016
      Bug description: When we click on the following path: Inventory/Radio Access Network/2G/2G BTS 2G BSC 2G Lac* 2G Rac* 3G Lac* 3G Rac*

      1. The text of "New Bts" must be changed to New BTS
      2. The text of "New Bsc" must be changed to New BSC
      3. The text of "2G Lac" must be changed to 2G LAC
      4. The text of "2G Rac" must be changed to 2G RAC
      5. The text of "New TwoG Lac" must be changed to New 2G LAC
      6. The text of "3G Lac" must be changed to 3G LAC
      7. The text of "3G Rac" must be changed to 3G RAC
      8. The text of "New ThreeG Lac" must be changed to New 3G LAC
      9. The text of "New ThreeG Rac" must be changed to New 3G RAC

      Either for MSC, MSS and MGW : New Msc to New MSC New Mss to New MSS and New Mgw to New MGW

      and for SGSN, GGSN, SGW, PGW and MME

      HSS and HLR, MFS, TRAU, TRAU Board

        Activity

        Transition Time In Source Status Execution Times Last Executer Last Execution Date
        Open Bug Open Bug Dev Scheduled Dev Scheduled
        2d 21h 47m 1 Abdel Rahman Tout 16/Mar/26 10:32 AM
        Ready for QA Ready for QA QA In Progress QA In Progress
        10d 23h 37m 1 Nemer Richmany 27/Mar/26 11:37 AM
        QA In Progress QA In Progress Reopened Reopened
        14s 1 Nemer Richmany 27/Mar/26 11:37 AM
        Reopened Reopened Dev Scheduled Dev Scheduled
        2d 20h 26m 1 Thierno Bah 30/Mar/26 9:03 AM
        Dev Scheduled Dev Scheduled Implementation in progress Implementation in progress
        11s 2 Thierno Bah 30/Mar/26 9:04 AM
        Implementation in progress Implementation in progress To Be Released To Be Released
        4h 2 Thierno Bah 30/Mar/26 1:04 PM
        To Be Released To Be Released Ready for QA Ready for QA
        1h 39m 2 Khaled Khalil 30/Mar/26 1:15 PM

          People

          • Assignee:
            Nemer Richmany
            Reporter:
            Nemer Richmany
          • Votes:
            0 Vote for this issue
            Watchers:
            3 Start watching this issue

            Dates

            • Due:
              Created:
              Updated:
              Resolved:
              Planned Start:
              Actual Start:

              Time Tracking

              Estimated:
              Original Estimate - Not Specified
              Not Specified
              Remaining:
              Remaining Estimate - 0 minutes
              0m
              Logged:
              Time Spent - 7 hours, 36 minutes
              7h 36m

                Drag and Drop