Details

    • Type: Task Task
    • Status: Done Done (View Workflow)
    • Priority: Normal Normal
    • Resolution: Unresolved
    • Affects Version/s: UCMDB 4.0.0.20
    • Fix Version/s: None
    • Component/s: UCMDB
    • Labels:
    • Customer:
      Mobinets

      Description

      When a user creates or edits zones and clicks “Save,” the zones are successfully persisted (no error is shown), but they do not render on the map afterward. This creates the impression that the save operation failed, even though the data may exist in the backend.

        Activity

        Bessem Manita made changes -
        Field Original Value New Value
        Gantt Options Milestone (set to milestone: having a due date but zero effort)
        Planned Start 2026-04-02 24:00 (milestone: set planned start date to due date)
        Planned End 2026-04-02 24:00 (milestone: set planned end date to due date)
        made changes -
        Description When a user creates or edits zones and clicks “Save,” the zones are successfully persisted (no error is shown), but they do not render on the map afterward. This creates the impression that the save operation failed, even though the data may exist in the backend.
        Mohamad Ghorghar made changes -
        Status To Do [ 10001 ] In Progress [ 3 ]
        Mohamad Ghorghar made changes -
        Remaining Estimate 0 minutes [ 0 ]
        Time Spent 1 day [ 28800 ]
        Worklog Id 295919 [ 295919 ]
        Mohamad Ghorghar made changes -
        Baseline Start 2026-04-02 24:00 (set baseline based of initial work logging)
        Baseline End 2026-04-02 24:00 (set baseline based of initial work logging)
        Mohamad Ghorghar made changes -
        Time Spent 1 day [ 28800 ] 2 days [ 57600 ]
        Worklog Id 295922 [ 295922 ]
        Mohamad Ghorghar made changes -
        Status In Progress [ 3 ] Done [ 10000 ]

          People

          • Assignee:
            Mohamad Ghorghar
            Reporter:
            Bessem Manita
          • Votes:
            0 Vote for this issue
            Watchers:
            2 Start watching this issue

            Dates

            • Due:
              Created:
              Updated:
              Planned Start:
              Planned End:
              Actual Start:
              Date of Baselining:

              Time Tracking

              Estimated:
              Original Estimate - Not Specified
              Not Specified
              Remaining:
              Remaining Estimate - 0 minutes
              0m
              Logged:
              Time Spent - 2 days
              2d