Details
-
Type:
Task
-
Status:
Done
(View Workflow)
-
Priority:
Normal
-
Resolution: Unresolved
-
Affects Version/s: None
-
Fix Version/s: None
-
Component/s: None
-
Customer:Mobinets
Description
Click to add description
Activity
-
- Time Spent:
- 1 day
-
- Generic view ui enhancement.
- Deletion Nep Status Attributes in Elements Status done.
| Field | Original Value | New Value |
|---|---|---|
| Gantt Options | Milestone (set to milestone: having a due date but zero effort) | |
| Planned Start | 2025-08-13 24:00 (milestone: set planned start date to due date) | |
| Planned End | 2025-08-13 24:00 (milestone: set planned end date to due date) |
| Remaining Estimate | 0 minutes [ 0 ] | |
| Time Spent | 1 day [ 28800 ] | |
| Worklog Id | 273508 [ 273508 ] |
| Baseline Start | 2025-08-13 24:00 (set baseline based of initial work logging) | |
| Baseline End | 2025-08-13 24:00 (set baseline based of initial work logging) |
| Status | To Do [ 10001 ] | Done [ 10000 ] |
-
- Time Spent:
- 4 hours
-
- fixing a bug related to 4g cell regarding the tracking area
| Time Spent | 1 day [ 28800 ] | 1 day, 4 hours [ 43200 ] |
| Worklog Id | 282480 [ 282480 ] |
| Transition | Time In Source Status | Execution Times | Last Executer | Last Execution Date | |||||
|---|---|---|---|---|---|---|---|---|---|
|
3d 2h 22m | 1 | Khaled Khalil | 08/Aug/25 11:23 AM |
|