Description
Dear Khaled Khalil,
Please assign a resource to check for below requirement.
it is required to add a "mass deletion" option in each of the Cell reports. So that, the outdated Cells can be removed from these reports.
below are the reports
2G Cells Report
3G Cells Report
4G Cells Report
Attachments
Activity
| Field | Original Value | New Value |
|---|---|---|
| Gantt Options | Milestone (set to milestone: having a due date but zero effort) | |
| Planned Start | 2025-04-30 24:00 (milestone: set planned start date to due date) | |
| Planned End | 2025-04-30 24:00 (milestone: set planned end date to due date) |
| Assignee | Khaled Khalil [ kkhalil ] | Diana Hamdouche [ dhamdouche ] |
| Remaining Estimate | 0 minutes [ 0 ] | |
| Time Spent | 1 hour [ 3600 ] | |
| Worklog Id | 265519 [ 265519 ] |
| Baseline Start | 2025-04-30 24:00 (set baseline based of initial work logging) | |
| Baseline End | 2025-04-30 24:00 (set baseline based of initial work logging) |
| Link | This issue blocks MOB-7010 [ MOB-7010 ] |
| Assignee | Diana Hamdouche [ dhamdouche ] | Aurobinda Panda [ apanda ] |
| Time Spent | 1 hour [ 3600 ] | 1 day, 1 hour [ 32400 ] |
| Worklog Id | 266810 [ 266810 ] |
| Time Spent | 1 day, 1 hour [ 32400 ] | 2 days, 1 hour [ 61200 ] |
| Worklog Id | 266811 [ 266811 ] |
| Time Spent | 2 days, 1 hour [ 61200 ] | 3 days, 1 hour [ 90000 ] |
| Worklog Id | 266812 [ 266812 ] |
| Status | Opened [ 1 ] | Need More Info [ 10011 ] |
| Status | Need More Info [ 10011 ] | Opened [ 1 ] |
| Status | Opened [ 1 ] | Pending Requirements [ 10300 ] |
| Status | Pending Requirements [ 10300 ] | Pending Design Session [ 10112 ] |
| Assignee | Aurobinda Panda [ apanda ] | Khaled Khalil [ kkhalil ] |
| Status | Pending Design Session [ 10112 ] | Dev Scheduled [ 10014 ] |
| Status | Dev Scheduled [ 10014 ] | Implementation in progress [ 10016 ] |
| Assignee | Khaled Khalil [ kkhalil ] | Abir Messaikeh [ amessaikeh ] |
| Status | Implementation in progress [ 10016 ] | To Be Released [ 10400 ] |
| Status | To Be Released [ 10400 ] | Ready for QA [ 10023 ] |
| Assignee | Abir Messaikeh [ amessaikeh ] | Aurobinda Panda [ apanda ] |
| Status | Ready for QA [ 10023 ] | QA In Progress [ 10015 ] |
| Assignee | Aurobinda Panda [ apanda ] | Abir Messaikeh [ amessaikeh ] |
| Status | QA In Progress [ 10015 ] | Closed [ 6 ] |
| Resolution | Fixed [ 1 ] |
| Time Spent | 3 days, 1 hour [ 90000 ] | 3 days, 1 hour, 30 minutes [ 91800 ] |
| Worklog Id | 266832 [ 266832 ] |
| Worklog Id | 266832 [ 266832 ] |