Details

    • Customer:
      Airtel India
    • Defect Category:
      Regression
    • Classification:
      Req. Tuning

      Description

      Name column in NEP 4G cell report is not reflecting, need to check the history how these column got removed .

      OLD 4G CELL REPORT ATTACHED

        Activity

        Srishti Kashyap logged work - 10/Oct/25 12:00 AM
        • Time Spent:
          3 hours
           

          column name not reflecting in 4gcell report, found the name aded during setid addition having same column discussed with marwaan same column is problem tried assigning different values column values not reflecting checking diffrent values and testing, added import module value name now now reflecting in report in gui and export csv commited the code

        Priyasha Tiwari made changes -
        Field Original Value New Value
        Gantt Options Milestone (set to milestone: having a due date but zero effort)
        Planned Start 2025-10-13 24:00 (milestone: set planned start date to due date)
        Planned End 2025-10-13 24:00 (milestone: set planned end date to due date)
        Priyasha Tiwari made changes -
        Description Name column in NEP 4G cell report is not reflecting, need to check the history how these column got removed . Name column in NEP 4G cell report is not reflecting, need to check the history how these column got removed .

        OLD 4G CELL REPORT ATTACHED
        Priyasha Tiwari made changes -
        Component/s NEP [ 16200 ]
        Priyasha Tiwari made changes -
        Labels NEP_D
        Priyasha Tiwari made changes -
        Attachment CN_4G_Cell_30-06.csv [ 119508 ]
        Priyasha Tiwari logged work - 12/Oct/25 12:00 AM
        • Time Spent:
          2 hours
           

          patch release to be applied and confirm by l2 .. mail initiated and checked the same

        Basant Kumar logged work - 13/Oct/25 12:00 AM
        • Time Spent:
          2 hours
           

          NEP_AIRTEL - Build 3.7.71.513 - Successful patch has been deployed .177 and DL DB configured on .177 .

        Hide
        added a comment -

        build 3.7.71.513 released fixing the code regression occured.

        Show
        added a comment - build 3.7.71.513 released fixing the code regression occured.
        Srishti Kashyap made changes -
        Status Open Bug [ 10108 ] Dev Scheduled [ 10014 ]
        Due Date 13/Oct/25 10/Oct/25
        Planned Start 13/Oct/25 12:00 AM 10/Oct/25 12:00 AM
        Planned End 13/Oct/25 12:00 AM 10/Oct/25 12:00 AM
        Srishti Kashyap made changes -
        Status Dev Scheduled [ 10014 ] Implementation in progress [ 10016 ]
        Assignee Khaled Khalil [ kkhalil ] Srishti Kashyap [ skashyap ]
        Srishti Kashyap made changes -
        Status Implementation in progress [ 10016 ] To Be Released [ 10400 ]
        Defect Category Regression [ 11213 ]
        Dev Verification Done Static Analysis,Unit Testing,Code Review [ 10700, 10701, 10702 ]
        Classification Req. Tuning [ 13204 ]
        Khaled Khalil made changes -
        Status To Be Released [ 10400 ] Ready for QA [ 10023 ]
        Assignee Srishti Kashyap [ skashyap ] Priyasha Tiwari [ ptiwari ]
        Srishti Kashyap made changes -
        Remaining Estimate 0 minutes [ 0 ]
        Time Spent 3 hours [ 10800 ]
        Worklog Id 280358 [ 280358 ]
        Srishti Kashyap made changes -
        Baseline Start 2025-10-10 24:00 (set baseline based of initial work logging)
        Baseline End 2025-10-10 24:00 (set baseline based of initial work logging)
        Basant Kumar made changes -
        Time Spent 3 hours [ 10800 ] 5 hours [ 18000 ]
        Worklog Id 280416 [ 280416 ]
        Hide
        Priyasha Tiwari added a comment -

        under testing wl-1day.

        Show
        Priyasha Tiwari added a comment - under testing wl-1day.
        Priyasha Tiwari logged work - 23/Oct/25 12:00 AM
        • Time Spent:
          1 hour
           

          Bug analysis

        Priyasha Tiwari made changes -
        Time Spent 5 hours [ 18000 ] 6 hours [ 21600 ]
        Worklog Id 281308 [ 281308 ]
        Priyasha Tiwari made changes -
        Time Spent 6 hours [ 21600 ] 1 day [ 28800 ]
        Worklog Id 281315 [ 281315 ]
        Priyasha Tiwari made changes -
        Status Ready for QA [ 10023 ] QA In Progress [ 10015 ]
        Hide
        Priyasha Tiwari added a comment -

        on test platform correction done, awaiting customer approval to apply the same on prod .

        Show
        Priyasha Tiwari added a comment - on test platform correction done, awaiting customer approval to apply the same on prod .
        Priyasha Tiwari made changes -
        Status QA In Progress [ 10015 ] Closed [ 6 ]
        Resolution Fixed [ 1 ]
        Transition Time In Source Status Execution Times Last Executer Last Execution Date
        Open Bug Open Bug Dev Scheduled Dev Scheduled
        2d 20h 2m 1 Srishti Kashyap 13/Oct/25 4:59 AM
        Dev Scheduled Dev Scheduled Implementation in progress Implementation in progress
        7s 1 Srishti Kashyap 13/Oct/25 4:59 AM
        Implementation in progress Implementation in progress To Be Released To Be Released
        22s 1 Srishti Kashyap 13/Oct/25 4:59 AM
        To Be Released To Be Released Ready for QA Ready for QA
        5h 2m 1 Khaled Khalil 13/Oct/25 10:01 AM
        Ready for QA Ready for QA QA In Progress QA In Progress
        16d 22h 40m 1 Priyasha Tiwari 30/Oct/25 7:42 AM
        QA In Progress QA In Progress Closed Closed
        42s 1 Priyasha Tiwari 30/Oct/25 7:43 AM
        Subversion JIRA

        Links Hierarchy

         Documentation

        Invalid license: EXPIRED

          People

          • Assignee:
            Priyasha Tiwari
            Reporter:
            Priyasha Tiwari
          • Votes:
            0 Vote for this issue
            Watchers:
            1 Start watching this issue

            Dates

            • Due:
              Created:
              Updated:
              Resolved:
              Planned Start:
              Planned End:
              Actual Start:
              Date of Baselining:

              Time Tracking

              Estimated:
              Original Estimate - Not Specified
              Not Specified
              Remaining:
              Remaining Estimate - 0 minutes
              0m
              Logged:
              Time Spent - 1 day
              1d

                Drag and Drop