Details

    • Customer:
      Zain Kuwait
    • Complexity:
      High
    • Product:
      NEP

      Description

      Dear Khaled,
      Please assign a resource to investigate the issue on the Kuwait test platform, where the consolidated report is not displaying any data despite showing 8 pages and records.

      @Manjit Kumar please share today's server log for Kuwait test platform.

        Activity

        Mostafa.kalawoun made changes -
        Field Original Value New Value
        Gantt Options Milestone (set to milestone: having a due date but zero effort)
        Planned Start 2025-10-20 24:00 (milestone: set planned start date to due date)
        Planned End 2025-10-20 24:00 (milestone: set planned end date to due date)
        Khaled Khalil made changes -
        Component/s Financial [ 16400 ]
        Mostafa Kalawoun made changes -
        Remaining Estimate 0 minutes [ 0 ]
        Time Spent 2 hours [ 7200 ]
        Worklog Id 280941 [ 280941 ]
        Mostafa.kalawoun made changes -
        Baseline Start 2025-10-20 24:00 (set baseline based of initial work logging)
        Baseline End 2025-10-20 24:00 (set baseline based of initial work logging)
        Wajdi Jomaa made changes -
        Status Open Bug [ 10108 ] Dev Scheduled [ 10014 ]
        Wajdi Jomaa made changes -
        Status Dev Scheduled [ 10014 ] Implementation in progress [ 10016 ]
        Assignee Khaled Khalil [ kkhalil ] Wajdi Jomaa [ wjomaa ]
        Wajdi Jomaa made changes -
        Attachment consolidated_update.txt [ 120413 ]
        Wajdi Jomaa made changes -
        Status Implementation in progress [ 10016 ] To Be Released [ 10400 ]
        Khaled Khalil made changes -
        Status To Be Released [ 10400 ] Ready for QA [ 10023 ]
        Assignee Wajdi Jomaa [ wjomaa ] Mostafa Kalawoun [ mostafa.kalawoun ]
        Manjit Kumar made changes -
        Time Spent 2 hours [ 7200 ] 5 hours [ 18000 ]
        Worklog Id 281449 [ 281449 ]
        Daljeet Singh Virdi made changes -
        Time Spent 5 hours [ 18000 ] 7 hours [ 25200 ]
        Worklog Id 281469 [ 281469 ]
        Abir Messaikeh made changes -
        Status Ready for QA [ 10023 ] QA In Progress [ 10015 ]
        Assignee Mostafa Kalawoun [ mostafa.kalawoun ] Abir Messaikeh [ amessaikeh ]
        Abir Messaikeh made changes -
        Status QA In Progress [ 10015 ] Closed [ 6 ]
        Resolution Fixed [ 1 ]

          People

          • Assignee:
            Abir Messaikeh
            Reporter:
            Mostafa Kalawoun
          • Votes:
            0 Vote for this issue
            Watchers:
            2 Start watching this issue

            Dates

            • Due:
              Created:
              Updated:
              Resolved:
              Planned Start:
              Planned End:
              Actual Start:
              Date of Baselining:

              Time Tracking

              Estimated:
              Original Estimate - Not Specified
              Not Specified
              Remaining:
              Remaining Estimate - 0 minutes
              0m
              Logged:
              Time Spent - 7 hours
              7h

                Drag and Drop