        Basant Kumar logged work - 13/Nov/25 12:00 AM
        • Time Spent:
          1 hour
           

          i have shared the logs from RJ circle to priyasha

        Srishti Kashyap logged work - 13/Nov/25 12:00 AM
        • Time Spent:
          4 hours
           

          checked the logs checked the code discussed with bessem priyasha integration found no main xml import done on rj last query execution also no addinfo only RB been imported

        Priyasha Tiwari made changes -
        Field Original Value New Value
        Gantt Options Milestone (set to milestone: having a due date but zero effort)
        Planned Start 2025-11-13 24:00 (milestone: set planned start date to due date)
        Planned End 2025-11-13 24:00 (milestone: set planned end date to due date)
        Priyasha Tiwari made changes -
        Labels nep_dev
        Priyasha Tiwari made changes -
        Description RE REPORT SHOWING 0 ROUTED SITES
        Priyasha Tiwari made changes -
        Description RE REPORT SHOWING 0 ROUTED SITES
        RB REPORT SHOWING 0 ROUTED SITES IN RJ CIRCLE
        Hide
        Priyasha Tiwari added a comment -

        LOGS ATTACHED

        Show
        Priyasha Tiwari added a comment - LOGS ATTACHED
        Priyasha Tiwari made changes -
        Attachment server.log.2025-11-12_RJ.tgz [ 121900 ]
        Marwan Kanaan made changes -
        Component/s NEP [ 16200 ]
        Basant Kumar made changes -
        Remaining Estimate 0 minutes [ 0 ]
        Time Spent 1 hour [ 3600 ]
        Worklog Id 283241 [ 283241 ]
        Bkumar made changes -
        Baseline Start 2025-11-13 24:00 (set baseline based of initial work logging)
        Baseline End 2025-11-13 24:00 (set baseline based of initial work logging)
        Basant Kumar logged work - 14/Nov/25 12:00 AM
        • Time Spent:
          1 hour
           

          we have run the import rb in RJ circles requested by priyasha for issues in RJ circles .

        Basant Kumar logged work - 14/Nov/25 12:00 AM
        • Time Spent:
          1 hour
           

          logs shared fom RJ circles

        Srishti Kashyap made changes -
        Time Spent 1 hour [ 3600 ] 5 hours [ 18000 ]
        Worklog Id 283314 [ 283314 ]
        Priyasha Tiwari logged work - 16/Nov/25 12:00 AM
        • Time Spent:
          6 hours
           

          call with L3 and integration.. deletion procedure executed and then manual import of XML and RB result verified

        Basant Kumar logged work - 17/Nov/25 12:00 AM
        • Time Spent:
          1 hour
           

          i have shared xml from RJ to priyasha

        Priyasha Tiwari logged work - 17/Nov/25 12:00 AM
        • Time Spent:
          1 day
           

          issue analysis and validation and call with internal team L3 and Aurobinda panda , customer connect every 2 hr .

        Srishti Kashyap logged work - 17/Nov/25 12:00 AM - edited
        • Time Spent:
          7 hours, 30 minutes
           

          worked on checking the data

        Hide
        Marwan Kanaan added a comment -

        dear priyasha kindly add details and ss.

        Show
        Marwan Kanaan added a comment - dear priyasha kindly add details and ss.
        Priyasha Tiwari logged work - 18/Nov/25 12:00 AM
        • Time Spent:
          1 day
           

          issue analysis and validation and call with internal team L3 and Aurobinda panda , customer connect every 2 hr .

        Aurobinda Panda logged work - 18/Nov/25 12:00 AM
        • Time Spent:
          4 hours
           

          Internal discussion with team and data check for missing IPs in dump,XML and NEP.

        Srishti Kashyap logged work - 18/Nov/25 12:00 AM
        • Time Spent:
          7 hours, 30 minutes
           

          checking the remote ip code and dependency as suggested by bessem

        Basant Kumar made changes -
        Time Spent 5 hours [ 18000 ] 6 hours [ 21600 ]
        Worklog Id 283728 [ 283728 ]
        Basant Kumar made changes -
        Time Spent 6 hours [ 21600 ] 7 hours [ 25200 ]
        Worklog Id 283729 [ 283729 ]
        Basant Kumar made changes -
        Time Spent 7 hours [ 25200 ] 1 day [ 28800 ]
        Worklog Id 283735 [ 283735 ]
        Priyasha Tiwari made changes -
        Time Spent 1 day [ 28800 ] 2 days [ 57600 ]
        Worklog Id 283742 [ 283742 ]
        Priyasha Tiwari made changes -
        Time Spent 2 days [ 57600 ] 3 days [ 86400 ]
        Worklog Id 283743 [ 283743 ]
        Priyasha Tiwari made changes -
        Time Spent 3 days [ 86400 ] 3 days, 6 hours [ 108000 ]
        Worklog Id 283744 [ 283744 ]
        Aurobinda Panda logged work - 19/Nov/25 12:00 AM
        • Time Spent:
          3 hours
           

          Routing issue checking

        Basant Kumar logged work - 19/Nov/25 12:00 AM
        • Time Spent:
          1 hour
           

          we have given permission Version
          Elementadditionalinfo
          Enodeb
          ranbsnode
          for this table to dev team .

        Srishti Kashyap logged work - 19/Nov/25 12:00 AM
        • Time Spent:
          7 hours, 30 minutes
           

          shared the feedback to bessem o remote ip dependency regarding logicalinterface creation

        Aurobinda Panda made changes -
        Time Spent 3 days, 6 hours [ 108000 ] 4 days, 2 hours [ 122400 ]
        Worklog Id 283800 [ 283800 ]
        Aurobinda Panda made changes -
        Time Spent 4 days, 2 hours [ 122400 ] 4 days, 5 hours [ 133200 ]
        Worklog Id 283819 [ 283819 ]
        Aurobinda Panda logged work - 20/Nov/25 12:00 AM - edited
        • Time Spent:
          2 hours
           

          Data checking.

        Aurobinda Panda made changes -
        Time Spent 4 days, 5 hours [ 133200 ] 4 days, 6 hours [ 136800 ]
        Worklog Id 283922 [ 283922 ]
        Aurobinda Panda logged work - 21/Nov/25 12:00 AM
        • Time Spent:
          3 hours
           

          Discussion with Internal Team and data check.

        Khaled Khalil made changes -
        Assignee Khaled Khalil [ kkhalil ] Srishti Kashyap [ skashyap ]
        Aurobinda Panda logged work - 24/Nov/25 12:00 AM
        • Time Spent:
          3 hours
           

          Issue checked and discussed with Priyasha. reverted to customer with details.

        Basant Kumar made changes -
        Time Spent 4 days, 6 hours [ 136800 ] 4 days, 7 hours [ 140400 ]
        Worklog Id 284139 [ 284139 ]
        Aurobinda Panda logged work - 25/Nov/25 12:00 AM
        • Time Spent:
          2 hours
           

          issue has been discussed with Internal team and reverted to customer for the issue.

        Priyasha Tiwari logged work - 25/Nov/25 12:00 AM
        • Time Spent:
          2 hours
           

          overall data validation includes core dump ip ,xml data and nep data , error validation and call internally

        Aurobinda Panda made changes -
        Time Spent 4 days, 7 hours [ 140400 ] 1 week, 2 hours [ 151200 ]
        Worklog Id 284202 [ 284202 ]
        Srishti Kashyap made changes -
        Time Spent 1 week, 2 hours [ 151200 ] 1 week, 1 day, 1 hour, 30 minutes [ 178200 ]
        Worklog Id 284258 [ 284258 ]
        Srishti Kashyap made changes -
        Worklog Id 284258 [ 284258 ]
        Srishti Kashyap made changes -
        Time Spent 1 week, 1 day, 1 hour, 30 minutes [ 178200 ] 1 week, 2 days, 1 hour [ 205200 ]
        Worklog Id 284260 [ 284260 ]
        Srishti Kashyap made changes -
        Time Spent 1 week, 2 days, 1 hour [ 205200 ] 1 week, 3 days, 30 minutes [ 232200 ]
        Worklog Id 284261 [ 284261 ]
        Aurobinda Panda made changes -
        Time Spent 1 week, 3 days, 30 minutes [ 232200 ] 1 week, 3 days, 2 hours, 30 minutes [ 239400 ]
        Worklog Id 284291 [ 284291 ]
        Aurobinda Panda made changes -
        Time Spent 1 week, 3 days, 2 hours, 30 minutes [ 239400 ] 1 week, 3 days, 3 hours, 30 minutes [ 243000 ]
        Worklog Id 283922 [ 283922 ]
        Aurobinda Panda made changes -
        Time Spent 1 week, 3 days, 3 hours, 30 minutes [ 243000 ] 1 week, 3 days, 6 hours, 30 minutes [ 253800 ]
        Worklog Id 284332 [ 284332 ]
        Aurobinda Panda logged work - 26/Nov/25 12:00 AM
        • Time Spent:
          3 hours
           

          Data check and internal discussion with team.

        Aurobinda Panda made changes -
        Time Spent 1 week, 3 days, 6 hours, 30 minutes [ 253800 ] 1 week, 4 days, 1 hour, 30 minutes [ 264600 ]
        Worklog Id 284439 [ 284439 ]
        Priyasha Tiwari logged work - 27/Nov/25 12:00 AM
        • Time Spent:
          1 hour
           

          RB TRIGGERED MANUALLY FOR SOME SAMPLE CASES AND DATA VALIDATION

        Priyasha Tiwari made changes -
        Time Spent 1 week, 4 days, 1 hour, 30 minutes [ 264600 ] 1 week, 4 days, 3 hours, 30 minutes [ 271800 ]
        Worklog Id 284739 [ 284739 ]
        Priyasha Tiwari made changes -
        Time Spent 1 week, 4 days, 3 hours, 30 minutes [ 271800 ] 1 week, 4 days, 4 hours, 30 minutes [ 275400 ]
        Worklog Id 284747 [ 284747 ]
        Priyasha Tiwari logged work - 01/Dec/25 12:00 AM
        • Time Spent:
          2 hours
           

          routing DIP again, validation and root cause analysis

        Priyasha Tiwari logged work - 02/Dec/25 12:00 AM
        • Time Spent:
          3 hours
           

          SAME ANALYSIS DID FOR AP CIRCLE AS IT RAISED BT THE CIUSTOMER ..DIP IN NO OF RB SITE COUNT

        Priyasha Tiwari made changes -
        Time Spent 1 week, 4 days, 4 hours, 30 minutes [ 275400 ] 1 week, 4 days, 6 hours, 30 minutes [ 282600 ]
        Worklog Id 285041 [ 285041 ]
        Priyasha Tiwari logged work - 03/Dec/25 12:00 AM
        • Time Spent:
          2 hours
           

          routing dip in AP and RJ circle validation

        Priyasha Tiwari made changes -
        Time Spent 1 week, 4 days, 6 hours, 30 minutes [ 282600 ] 2 weeks, 30 minutes [ 289800 ]
        Worklog Id 285117 [ 285117 ]
        Priyasha Tiwari made changes -
        Time Spent 2 weeks, 30 minutes [ 289800 ] 2 weeks, 3 hours, 30 minutes [ 300600 ]
        Worklog Id 285345 [ 285345 ]
        Abir Messaikeh made changes -
        Status Open Bug [ 10108 ] Dev Scheduled [ 10014 ]
        Abir Messaikeh made changes -
        Issue Type Bug [ 1 ] CR [ 10900 ]
        Workflow Mobinets_Dev_BugWF_J4.4 [ 198300 ] Mobinets_Dev_WF_J4.4 [ 201711 ]
        Abir Messaikeh made changes -
        Issue Type CR [ 10900 ] Bug [ 1 ]
        Workflow Mobinets_Dev_WF_J4.4 [ 201711 ] Mobinets_Dev_BugWF_J4.4 [ 201712 ]
        Khaled Khalil made changes -
        Status Dev Scheduled [ 10014 ] Implementation in progress [ 10016 ]
        Assignee Srishti Kashyap [ skashyap ] Khaled Khalil [ kkhalil ]
        Khaled Khalil made changes -
        Status Implementation in progress [ 10016 ] Rejected [ 10100 ]
        Assignee Khaled Khalil [ kkhalil ] Priyasha Tiwari [ ptiwari ]
        Resolution Cancelled [ 10100 ]
        Khaled Khalil made changes -
        Status Rejected [ 10100 ] Cancelled [ 10013 ]
        Transition Time In Source Status Execution Times Last Executer Last Execution Date
        Open Bug Open Bug Dev Scheduled Dev Scheduled
        47d 10h 45m 1 Abir Messaikeh 30/Dec/25 2:14 PM
        Dev Scheduled Dev Scheduled Implementation in progress Implementation in progress
        6m 52s 1 Khaled Khalil 30/Dec/25 2:21 PM
        Implementation in progress Implementation in progress Rejected Rejected
        25s 1 Khaled Khalil 30/Dec/25 2:21 PM
        Rejected Rejected Cancelled Cancelled
        13s 1 Khaled Khalil 30/Dec/25 2:22 PM
        Subversion JIRA

        Links Hierarchy

         Documentation

        Invalid license: EXPIRED

          People

          • Assignee:
            Priyasha Tiwari
            Reporter:
            Priyasha Tiwari
            Rejected By:
            Khaled Khalil
          • Votes:
            0 Vote for this issue
            Watchers:
            2 Start watching this issue

            Dates

            • Due:
              Created:
              Updated:
              Resolved:
              Planned Start:
              Planned End:
              Actual Start:
              Date of Baselining:

              Time Tracking

              Estimated:
              Original Estimate - Not Specified
              Not Specified
              Remaining:
              Remaining Estimate - 0 minutes
              0m
              Logged:
              Time Spent - 2 weeks, 3 hours, 30 minutes
              2w 3h 30m

                Drag and Drop