Details

    • Customer:
      Airtel India

      Description

      RB REPORT SHOWING 0 ROUTED SITES IN RJ CIRCLE

        Activity

        Priyasha Tiwari made changes -
        Field Original Value New Value
        Gantt Options Milestone (set to milestone: having a due date but zero effort)
        Planned Start 2025-11-13 24:00 (milestone: set planned start date to due date)
        Planned End 2025-11-13 24:00 (milestone: set planned end date to due date)
        Priyasha Tiwari made changes -
        Labels nep_dev
        Priyasha Tiwari made changes -
        Description RE REPORT SHOWING 0 ROUTED SITES
        Priyasha Tiwari made changes -
        Description RE REPORT SHOWING 0 ROUTED SITES
        RB REPORT SHOWING 0 ROUTED SITES IN RJ CIRCLE
        Priyasha Tiwari made changes -
        Attachment server.log.2025-11-12_RJ.tgz [ 121900 ]
        Marwan Kanaan made changes -
        Component/s NEP [ 16200 ]
        Basant Kumar made changes -
        Remaining Estimate 0 minutes [ 0 ]
        Time Spent 1 hour [ 3600 ]
        Worklog Id 283241 [ 283241 ]
        Bkumar made changes -
        Baseline Start 2025-11-13 24:00 (set baseline based of initial work logging)
        Baseline End 2025-11-13 24:00 (set baseline based of initial work logging)
        Srishti Kashyap made changes -
        Time Spent 1 hour [ 3600 ] 5 hours [ 18000 ]
        Worklog Id 283314 [ 283314 ]
        Basant Kumar made changes -
        Time Spent 5 hours [ 18000 ] 6 hours [ 21600 ]
        Worklog Id 283728 [ 283728 ]
        Basant Kumar made changes -
        Time Spent 6 hours [ 21600 ] 7 hours [ 25200 ]
        Worklog Id 283729 [ 283729 ]
        Basant Kumar made changes -
        Time Spent 7 hours [ 25200 ] 1 day [ 28800 ]
        Worklog Id 283735 [ 283735 ]
        Priyasha Tiwari made changes -
        Time Spent 1 day [ 28800 ] 2 days [ 57600 ]
        Worklog Id 283742 [ 283742 ]
        Priyasha Tiwari made changes -
        Time Spent 2 days [ 57600 ] 3 days [ 86400 ]
        Worklog Id 283743 [ 283743 ]
        Priyasha Tiwari made changes -
        Time Spent 3 days [ 86400 ] 3 days, 6 hours [ 108000 ]
        Worklog Id 283744 [ 283744 ]
        Aurobinda Panda made changes -
        Time Spent 3 days, 6 hours [ 108000 ] 4 days, 2 hours [ 122400 ]
        Worklog Id 283800 [ 283800 ]
        Aurobinda Panda made changes -
        Time Spent 4 days, 2 hours [ 122400 ] 4 days, 5 hours [ 133200 ]
        Worklog Id 283819 [ 283819 ]
        Aurobinda Panda made changes -
        Time Spent 4 days, 5 hours [ 133200 ] 4 days, 6 hours [ 136800 ]
        Worklog Id 283922 [ 283922 ]
        Khaled Khalil made changes -
        Assignee Khaled Khalil [ kkhalil ] Srishti Kashyap [ skashyap ]
        Basant Kumar made changes -
        Time Spent 4 days, 6 hours [ 136800 ] 4 days, 7 hours [ 140400 ]
        Worklog Id 284139 [ 284139 ]
        Aurobinda Panda made changes -
        Time Spent 4 days, 7 hours [ 140400 ] 1 week, 2 hours [ 151200 ]
        Worklog Id 284202 [ 284202 ]
        Srishti Kashyap made changes -
        Time Spent 1 week, 2 hours [ 151200 ] 1 week, 1 day, 1 hour, 30 minutes [ 178200 ]
        Worklog Id 284258 [ 284258 ]
        Srishti Kashyap made changes -
        Worklog Id 284258 [ 284258 ]
        Srishti Kashyap made changes -
        Time Spent 1 week, 1 day, 1 hour, 30 minutes [ 178200 ] 1 week, 2 days, 1 hour [ 205200 ]
        Worklog Id 284260 [ 284260 ]
        Srishti Kashyap made changes -
        Time Spent 1 week, 2 days, 1 hour [ 205200 ] 1 week, 3 days, 30 minutes [ 232200 ]
        Worklog Id 284261 [ 284261 ]
        Aurobinda Panda made changes -
        Time Spent 1 week, 3 days, 30 minutes [ 232200 ] 1 week, 3 days, 2 hours, 30 minutes [ 239400 ]
        Worklog Id 284291 [ 284291 ]
        Aurobinda Panda made changes -
        Time Spent 1 week, 3 days, 2 hours, 30 minutes [ 239400 ] 1 week, 3 days, 3 hours, 30 minutes [ 243000 ]
        Worklog Id 283922 [ 283922 ]
        Aurobinda Panda made changes -
        Time Spent 1 week, 3 days, 3 hours, 30 minutes [ 243000 ] 1 week, 3 days, 6 hours, 30 minutes [ 253800 ]
        Worklog Id 284332 [ 284332 ]
        Aurobinda Panda made changes -
        Time Spent 1 week, 3 days, 6 hours, 30 minutes [ 253800 ] 1 week, 4 days, 1 hour, 30 minutes [ 264600 ]
        Worklog Id 284439 [ 284439 ]
        Priyasha Tiwari made changes -
        Time Spent 1 week, 4 days, 1 hour, 30 minutes [ 264600 ] 1 week, 4 days, 3 hours, 30 minutes [ 271800 ]
        Worklog Id 284739 [ 284739 ]
        Priyasha Tiwari made changes -
        Time Spent 1 week, 4 days, 3 hours, 30 minutes [ 271800 ] 1 week, 4 days, 4 hours, 30 minutes [ 275400 ]
        Worklog Id 284747 [ 284747 ]
        Priyasha Tiwari made changes -
        Time Spent 1 week, 4 days, 4 hours, 30 minutes [ 275400 ] 1 week, 4 days, 6 hours, 30 minutes [ 282600 ]
        Worklog Id 285041 [ 285041 ]
        Priyasha Tiwari made changes -
        Time Spent 1 week, 4 days, 6 hours, 30 minutes [ 282600 ] 2 weeks, 30 minutes [ 289800 ]
        Worklog Id 285117 [ 285117 ]
        Priyasha Tiwari made changes -
        Time Spent 2 weeks, 30 minutes [ 289800 ] 2 weeks, 3 hours, 30 minutes [ 300600 ]
        Worklog Id 285345 [ 285345 ]
        Abir Messaikeh made changes -
        Status Open Bug [ 10108 ] Dev Scheduled [ 10014 ]
        Abir Messaikeh made changes -
        Issue Type Bug [ 1 ] CR [ 10900 ]
        Workflow Mobinets_Dev_BugWF_J4.4 [ 198300 ] Mobinets_Dev_WF_J4.4 [ 201711 ]
        Abir Messaikeh made changes -
        Issue Type CR [ 10900 ] Bug [ 1 ]
        Workflow Mobinets_Dev_WF_J4.4 [ 201711 ] Mobinets_Dev_BugWF_J4.4 [ 201712 ]
        Khaled Khalil made changes -
        Status Dev Scheduled [ 10014 ] Implementation in progress [ 10016 ]
        Assignee Srishti Kashyap [ skashyap ] Khaled Khalil [ kkhalil ]
        Khaled Khalil made changes -
        Status Implementation in progress [ 10016 ] Rejected [ 10100 ]
        Assignee Khaled Khalil [ kkhalil ] Priyasha Tiwari [ ptiwari ]
        Resolution Cancelled [ 10100 ]
        Khaled Khalil made changes -
        Status Rejected [ 10100 ] Cancelled [ 10013 ]

          People

          • Assignee:
            Priyasha Tiwari
            Reporter:
            Priyasha Tiwari
            Rejected By:
            Khaled Khalil
          • Votes:
            0 Vote for this issue
            Watchers:
            2 Start watching this issue

            Dates

            • Due:
              Created:
              Updated:
              Resolved:
              Planned Start:
              Planned End:
              Actual Start:
              Date of Baselining:

              Time Tracking

              Estimated:
              Original Estimate - Not Specified
              Not Specified
              Remaining:
              Remaining Estimate - 0 minutes
              0m
              Logged:
              Time Spent - 2 weeks, 3 hours, 30 minutes
              2w 3h 30m

                Drag and Drop