Details

    • Customer:
      OMAN-Tel
    • Complexity:
      High
    • Severity:
      Critical
    • Product:
      NEP
    • REQUESTER:
      INTERNAL

      Description

      The RB report in NEP not showing correct result. the Number of S1-U and S1-MME Interfaces Routes with MW cloud or IP cloud available in RAN Summary tab are not matching with no of interfaces in RAN IP tab in RB report. This mismatch is leading to wrong analysis.

      I have attached SS from both the tabs from RB report.

      Note: The testing can't be done for sample node. As the No of interfaces will be very less and can't give the correct result.

        Activity

        Aurobinda Panda made changes -
        Field Original Value New Value
        Gantt Options Milestone (set to milestone: having a due date but zero effort)
        Planned Start 2025-12-19 24:00 (milestone: set planned start date to due date)
        Planned End 2025-12-19 24:00 (milestone: set planned end date to due date)
        Khaled Khalil made changes -
        Assignee Khaled Khalil [ kkhalil ] Bessem Manita [ bmanita ]
        Aurobinda Panda made changes -
        Summary RB report not showing correct Cloud Data OT | RB report not showing correct Cloud Data
        Bessem Manita made changes -
        Status Open Bug [ 10108 ] Dev Scheduled [ 10014 ]
        Bessem Manita made changes -
        Status Dev Scheduled [ 10014 ] Implementation in progress [ 10016 ]
        Bessem Manita made changes -
        Status Implementation in progress [ 10016 ] To Be Released [ 10400 ]
        Aurobinda Panda made changes -
        Remaining Estimate 0 minutes [ 0 ]
        Time Spent 1 hour, 30 minutes [ 5400 ]
        Worklog Id 286366 [ 286366 ]
        Aurobinda Panda made changes -
        Baseline Start 2025-12-19 24:00 (set baseline based of initial work logging)
        Baseline End 2025-12-19 24:00 (set baseline based of initial work logging)
        Khaled Khalil made changes -
        Status To Be Released [ 10400 ] Ready for QA [ 10023 ]
        Assignee Bessem Manita [ bmanita ] Aurobinda Panda [ apanda ]
        Khaled Khalil made changes -
        Component/s NEP [ 16200 ]
        Aurobinda Panda made changes -
        Status Ready for QA [ 10023 ] QA In Progress [ 10015 ]
        Aurobinda Panda made changes -
        Status QA In Progress [ 10015 ] Closed [ 6 ]
        Resolution Fixed [ 1 ]
        Aurobinda Panda made changes -
        Time Spent 1 hour, 30 minutes [ 5400 ] 3 hours, 30 minutes [ 12600 ]
        Worklog Id 286503 [ 286503 ]

          People

          • Assignee:
            Aurobinda Panda
            Reporter:
            Aurobinda Panda
          • Votes:
            0 Vote for this issue
            Watchers:
            2 Start watching this issue

            Dates

            • Due:
              Created:
              Updated:
              Resolved:
              Planned Start:
              Planned End:
              Actual Start:
              Date of Baselining:

              Time Tracking

              Estimated:
              Original Estimate - Not Specified
              Not Specified
              Remaining:
              Remaining Estimate - 0 minutes
              0m
              Logged:
              Time Spent - 3 hours, 30 minutes
              3h 30m

                Drag and Drop