      Kindly support to check the below Item not available in Unmapped Report. Barcode(20116016). Pl find attached doc with all the snippets.

        Activity

        DSVirdi made changes -
        Field Original Value New Value
        Gantt Options Milestone (set to milestone: having a due date but zero effort)
        Planned Start 2025-12-31 24:00 (milestone: set planned start date to due date)
        Planned End 2025-12-31 24:00 (milestone: set planned end date to due date)
        Daljeet Singh Virdi made changes -
        Attachment FR import issue.docx [ 125104 ]
        Bessem Manita made changes -
        Attachment Screenshot 2025-12-30 120344.png [ 125116 ]
        Bessem Manita made changes -
        Status Open Bug [ 10108 ] Dev Scheduled [ 10014 ]
        Khaled Khalil made changes -
        Assignee Khaled Khalil [ kkhalil ] Bessem Manita [ bmanita ]
        Manjit Kumar made changes -
        Remaining Estimate 0 minutes [ 0 ]
        Time Spent 2 hours, 30 minutes [ 9000 ]
        Worklog Id 287815 [ 287815 ]
        Manjit Kumar made changes -
        Baseline Start 2025-12-31 24:00 (set baseline based of initial work logging)
        Baseline End 2025-12-31 24:00 (set baseline based of initial work logging)
        Manjit Kumar made changes -
        Remaining Estimate 0 minutes [ 0 ] 30 minutes [ 1800 ]
        Time Spent 2 hours, 30 minutes [ 9000 ] 2 hours [ 7200 ]
        Worklog Id 287815 [ 287815 ]
        Bessem Manita made changes -
        Status Dev Scheduled [ 10014 ] Open Bug [ 10108 ]
        Assignee Bessem Manita [ bmanita ] Daljeet Singh Virdi [ dsvirdi ]
        Bessem Manita made changes -
        Status Open Bug [ 10108 ] Dev Scheduled [ 10014 ]
        Bessem Manita made changes -
        Status Dev Scheduled [ 10014 ] Implementation in progress [ 10016 ]
        Assignee Daljeet Singh Virdi [ dsvirdi ] Bessem Manita [ bmanita ]
        Bessem Manita made changes -
        Status Implementation in progress [ 10016 ] To Be Released [ 10400 ]
        Khaled Khalil made changes -
        Status To Be Released [ 10400 ] Ready for QA [ 10023 ]
        Assignee Bessem Manita [ bmanita ] Daljeet Singh Virdi [ dsvirdi ]
        Daljeet Singh Virdi made changes -
        Remaining Estimate 30 minutes [ 1800 ] 0 minutes [ 0 ]
        Time Spent 2 hours [ 7200 ] 3 hours [ 10800 ]
        Worklog Id 288044 [ 288044 ]
        Daljeet Singh Virdi made changes -
        Time Spent 3 hours [ 10800 ] 5 hours [ 18000 ]
        Worklog Id 288044 [ 288044 ]
        Daljeet Singh Virdi made changes -
        Worklog Id 288044 [ 288044 ]
        Daljeet Singh Virdi made changes -
        Status Ready for QA [ 10023 ] QA In Progress [ 10015 ]
        Daljeet Singh Virdi made changes -
        Status QA In Progress [ 10015 ] Closed [ 6 ]
        Resolution Fixed [ 1 ]

          People

          • Assignee:
            Daljeet Singh Virdi
            Reporter:
            Daljeet Singh Virdi
          • Votes:
            0 Vote for this issue
            Watchers:
            2 Start watching this issue

            Dates

            • Due:
              Created:
              Updated:
              Resolved:
              Planned Start:
              Planned End:
              Actual Start:
              Date of Baselining:

              Time Tracking

              Estimated:
              Original Estimate - Not Specified
              Not Specified
              Remaining:
              Remaining Estimate - 0 minutes
              0m
              Logged:
              Time Spent - 5 hours
              5h