      We are trying to approve one Passive asset under L3 for retirement. ;

        Activity

        Manjit Kumar logged work - 24/Feb/26 12:00 AM
        • Time Spent:
          2 hours
           

          Analyze the log and found issue of resfreshAssetViews then informed to L3 and shared details along with log.

        Daljeet Singh Virdi logged work - 24/Feb/26 12:00 AM
        • Time Spent:
          5 hours
           

          Customer raised issue with WF, first it was asked to check the table space, later got raised with Dev team, Also we found another issue that is performance issue, also raised with Dev team.

        DSVirdi made changes -
        Field Original Value New Value
        Gantt Options Milestone (set to milestone: having a due date but zero effort)
        Planned Start 2026-02-26 24:00 (milestone: set planned start date to due date)
        Planned End 2026-02-26 24:00 (milestone: set planned end date to due date)
        Daljeet Singh Virdi made changes -
        Attachment WF error.jpg [ 128904 ]
        Manjit Kumar made changes -
        Remaining Estimate 0 minutes [ 0 ]
        Time Spent 2 hours [ 7200 ]
        Worklog Id 292545 [ 292545 ]
        Manjit Kumar made changes -
        Baseline Start 2026-02-26 24:00 (set baseline based of initial work logging)
        Baseline End 2026-02-26 24:00 (set baseline based of initial work logging)
        Daljeet Singh Virdi logged work - 02/Mar/26 12:00 AM
        • Time Spent:
          1 hour
           

          Check for the update

        Khaled Khalil made changes -
        Component/s Financial [ 16400 ]
        Component/s WF [ 16401 ]
        Hide
        Mohamed Benadel added a comment -

        Issue fixed , will be released in patch : 3.7.1.706

        patch deployment is required

        • changes : changed the process of retirement on the L3 approval to prevent TAG and RFID Duplication .
        Show
        Mohamed Benadel added a comment - Issue fixed , will be released in patch : 3.7.1.706 patch deployment is required changes : changed the process of retirement on the L3 approval to prevent TAG and RFID Duplication .
        Manjit Kumar logged work - 03/Mar/26 12:00 AM - edited
        • Time Spent:
          2 hours, 30 minutes
           

          As per request, patch has been applied. Also made MOP and shared with cybermak team along with patch.

        Daljeet Singh Virdi logged work - 03/Mar/26 12:00 AM
        • Time Spent:
          5 hours
           

          Testing with document prepared

        Khaled Khalil made changes -
        Status Open Bug [ 10108 ] Dev Scheduled [ 10014 ]
        Khaled Khalil made changes -
        Status Dev Scheduled [ 10014 ] Implementation in progress [ 10016 ]
        Khaled Khalil made changes -
        Status Implementation in progress [ 10016 ] To Be Released [ 10400 ]
        Khaled Khalil made changes -
        Status To Be Released [ 10400 ] Ready for QA [ 10023 ]
        Assignee Khaled Khalil [ kkhalil ] Daljeet Singh Virdi [ dsvirdi ]
        Manjit Kumar logged work - 05/Mar/26 12:00 AM
        • Time Spent:
          1 hour, 30 minutes
           

          Join call with cybermak team to discuss ongoing task.

        Manjit Kumar made changes -
        Time Spent 2 hours [ 7200 ] 3 hours [ 10800 ]
        Worklog Id 293232 [ 293232 ]
        Manjit Kumar made changes -
        Worklog Id 293232 [ 293232 ]
        Manjit Kumar made changes -
        Time Spent 3 hours [ 10800 ] 4 hours, 30 minutes [ 16200 ]
        Worklog Id 293232 [ 293232 ]
        Manjit Kumar made changes -
        Time Spent 4 hours, 30 minutes [ 16200 ] 6 hours [ 21600 ]
        Worklog Id 293236 [ 293236 ]
        Daljeet Singh Virdi made changes -
        Time Spent 6 hours [ 21600 ] 7 hours [ 25200 ]
        Worklog Id 293629 [ 293629 ]
        Daljeet Singh Virdi made changes -
        Time Spent 7 hours [ 25200 ] 1 day, 4 hours [ 43200 ]
        Worklog Id 293631 [ 293631 ]
        Daljeet Singh Virdi made changes -
        Time Spent 1 day, 4 hours [ 43200 ] 2 days, 1 hour [ 61200 ]
        Worklog Id 293666 [ 293666 ]
        Daljeet Singh Virdi made changes -
        Status Ready for QA [ 10023 ] QA In Progress [ 10015 ]
        Daljeet Singh Virdi made changes -
        Status QA In Progress [ 10015 ] Closed [ 6 ]
        Resolution Fixed [ 1 ]
        Transition Time In Source Status Execution Times Last Executer Last Execution Date
        Open Bug Open Bug Dev Scheduled Dev Scheduled
        7d 7h 7m 1 Khaled Khalil 03/Mar/26 12:22 PM
        Dev Scheduled Dev Scheduled Implementation in progress Implementation in progress
        6s 1 Khaled Khalil 03/Mar/26 12:22 PM
        Implementation in progress Implementation in progress To Be Released To Be Released
        9s 1 Khaled Khalil 03/Mar/26 12:22 PM
        To Be Released To Be Released Ready for QA Ready for QA
        5s 1 Khaled Khalil 03/Mar/26 12:22 PM
        Ready for QA Ready for QA QA In Progress QA In Progress
        8d 15h 52m 1 Daljeet Singh Virdi 12/Mar/26 4:15 AM
        QA In Progress QA In Progress Closed Closed
        11s 1 Daljeet Singh Virdi 12/Mar/26 4:15 AM
        Subversion JIRA

        Links Hierarchy

         Documentation

        Invalid license: EXPIRED

          People

          • Assignee:
            Daljeet Singh Virdi
            Reporter:
            Daljeet Singh Virdi
          • Votes:
            0 Vote for this issue
            Watchers:
            2 Start watching this issue

            Dates

            • Due:
              Created:
              Updated:
              Resolved:
              Planned Start:
              Planned End:
              Actual Start:
              Date of Baselining:

              Time Tracking

              Estimated:
              Original Estimate - Not Specified
              Not Specified
              Remaining:
              Remaining Estimate - 0 minutes
              0m
              Logged:
              Time Spent - 2 days, 1 hour