      Could you please assign a DEV resource to investigate the following issue as outlined below?

      1. The "Manufacturer" header is showing as blank in the NEP reports for cabinet and shelf, although it is correctly listed in the XML under the respective cabinet and shelf.
      2. For the board and inventory reports, the manufacturer is correctly displayed in the NEP, which is correct.

      XML File: 2024-12-09-09.33.09_ZainKsa

      Please find the required XML and NEP snippets for your reference:

      XML Snippet:

      Nodecabinet Nodeshelf

      Nodeboard

      NEP Snippet:

      Cabinet Report Shelf Report

      Board Report & Inventory report (Manufacturer is available i.e., ok)

      Looking forward to your confirmation and assistance on this matter.

      Best regards,
      Indrasan

      Issue Links

        Activity

        Mustapha Al-Hage made changes -
        Time Spent 1 hour, 30 minutes [ 5400 ] 2 hours, 30 minutes [ 9000 ]
        Worklog Id 258551 [ 258551 ]
        Indrasan Yadav made changes -
        Time Spent 30 minutes [ 1800 ] 1 hour, 30 minutes [ 5400 ]
        Worklog Id 258714 [ 258714 ]
        Indrasan Yadav made changes -
        Status QA In Progress [ 10015 ] Closed [ 6 ]
        Resolution Fixed [ 1 ]
        Indrasan Yadav made changes -
        Status Ready for QA [ 10023 ] QA In Progress [ 10015 ]
        Indrasan Yadav made changes -
        Link This issue blocks ZKU-94 [ ZKU-94 ]
        Khaled Khalil made changes -
        Status To Be Released [ 10400 ] Ready for QA [ 10023 ]
        Mustapha Al-Hage made changes -
        Assignee Mustapha Al-Hage [ malhage ] Indrasan Yadav [ iyadav ]
        Mustapha Al-Hage made changes -
        Status Implementation in progress [ 10016 ] To Be Released [ 10400 ]
        Mustapha Al-Hage made changes -
        Status Dev Scheduled [ 10014 ] Implementation in progress [ 10016 ]
        Mustapha Al-Hage made changes -
        Status Open Bug [ 10108 ] Dev Scheduled [ 10014 ]
        Mustapha Al-Hage made changes -
        Baseline Start 2024-12-23 24:00 (set baseline based of initial work logging)
        Baseline End 2024-12-23 24:00 (set baseline based of initial work logging)
        Mustapha Al-Hage made changes -
        Remaining Estimate 0 minutes [ 0 ]
        Time Spent 30 minutes [ 1800 ]
        Worklog Id 258551 [ 258551 ]
        Khaled Khalil made changes -
        Assignee Khaled Khalil [ kkhalil ] Mustapha Al-Hage [ malhage ]
        Indrasan Yadav made changes -
        Field Original Value New Value
        Gantt Options Milestone (set to milestone: having a due date but zero effort)
        Planned Start 2024-12-23 24:00 (milestone: set planned start date to due date)
        Planned End 2024-12-23 24:00 (milestone: set planned end date to due date)

          People

          • Assignee:
            Indrasan Yadav
            Reporter:
            Indrasan Yadav
          • Votes:
            0 Vote for this issue
            Watchers:
            2 Start watching this issue

            Dates

            • Due:
              Created:
              Updated:
              Resolved:
              Planned Start:
              Planned End:
              Actual Start:
              Date of Baselining:

              Time Tracking

              Estimated:
              Original Estimate - Not Specified
              Not Specified
              Remaining:
              Remaining Estimate - 0 minutes
              0m
              Logged:
              Time Spent - 2 hours, 30 minutes
              2h 30m