Details
-
Type:
Task
-
Status:
Closed
(View Workflow)
-
Priority:
Normal
-
Resolution: Fixed
-
Customer:Ooreedo Tunisia
Activity
| Field | Original Value | New Value |
|---|---|---|
| Gantt Options | Milestone (set to milestone: having a due date but zero effort) | |
| Planned Start | 2025-08-31 24:00 (milestone: set planned start date to due date) | |
| Planned End | 2025-08-31 24:00 (milestone: set planned end date to due date) |
| Remaining Estimate | 0 minutes [ 0 ] | |
| Time Spent | 30 minutes [ 1800 ] | |
| Worklog Id | 273413 [ 273413 ] |
| Baseline Start | 2025-08-31 24:00 (set baseline based of initial work logging) | |
| Baseline End | 2025-08-31 24:00 (set baseline based of initial work logging) |
| Status | Opened [ 1 ] | In Progress [ 3 ] |
| Assignee | Bassem Sabbagh [ bsabbagh ] | Indrasan Yadav [ iyadav ] |
| Status | In Progress [ 3 ] | Resolved [ 5 ] |
| Resolution | Done [ 10000 ] |
| Status | Resolved [ 5 ] | Closed [ 6 ] |
| Resolution | Done [ 10000 ] | |
| Status | Closed [ 6 ] | Reopened [ 4 ] |
| Time Spent | 30 minutes [ 1800 ] | 1 hour [ 3600 ] |
| Worklog Id | 273733 [ 273733 ] |
| Status | Reopened [ 4 ] | Resolved [ 5 ] |
| Resolution | Fixed [ 1 ] |
| Status | Resolved [ 5 ] | Closed [ 6 ] |