[LS-1015] NEP update date not working as required - CIRCLE- JK Created: 20/Mar/26  Updated: 06/Apr/26  Due: 23/Mar/26  Resolved: 06/Apr/26

Status: Cancelled
Project: L3 Support
Component/s: NEP
Affects Version/s: None
Fix Version/s: None

Type: Bug Priority: Normal
Reporter: Priyasha Tiwari Assignee: Priyasha Tiwari
Resolution: Fixed Votes: 0
Labels: NEP_D
Remaining Estimate: 0 minutes
Time Spent: 7 hours
Original Estimate: Not Specified

Attachments: PNG File JK UPDATE DATE ISSUE.png     PNG File jk update date issue error ss.png    
Customer:
Airtel India
Planned Start:
Planned End:
Actual Start:
Date of Baselining:

 Description   

node FJMU950 is available in the XML, but it is not getting updated in the NEP report. CIRCLE- JK



 Comments   
Comment by Priyasha Tiwari [ 20/Mar/26 ]

error screenshot will attach

Comment by Priyasha Tiwari [ 06/Apr/26 ]

fixed on its own