[LS-505] Zain KW | Default Date in Reports Created: 14/Jul/25  Updated: 12/Feb/26  Due: 17/Jul/25  Resolved: 12/Feb/26

Status: Closed
Project: L3 Support
Component/s: Financial
Affects Version/s: None
Fix Version/s: None

Type: CR Priority: Normal
Reporter: Daljeet Singh Virdi Assignee: Abir Messaikeh
Resolution: Fixed Votes: 0
Labels: None
Σ Remaining Estimate: 0 minutes Remaining Estimate: 0 minutes
Σ Time Spent: 1 day, 5 hours, 30 minutes Time Spent: 1 day, 5 hours, 30 minutes
Σ Original Estimate: Not Specified Original Estimate: Not Specified

Attachments: PNG File FR Date.png    
Sub-Tasks:
Key
Summary
Type
Status
Assignee
LS-688 Zain KW | Default Date in Reports Des... Technical task Cancelled Khaled Khalil  
LS-506 Zain KW | Default Date in Reports Req... Technical task Cancelled Khaled Khalil  
LS-689 Zain KW | Default Date in Reports : T... Technical task Cancelled Khaled Khalil  
Customer:
Zain Kuwait
Planned Start:
Planned End:
Actual Start:
Date of Baselining:

 Description   

Kindly align the resource for the below mentioned CR in Zain KW:

The customer has requested an enhancement to the NEP Preferences functionality. Specifically, they would like the ability to set a default start date for the Financial Report to January 1980 in Financial Report and Consolidated Report.
Requirements:
• Default Date Behavior: The system should allow the default report date to be pre-set to January 1980 via NEP Preferences.
• User Flexibility: Users must still retain the ability to manually modify the start and end dates directly within the Financial Report screen, as currently supported.
• Persistence: The default date should persist across sessions unless changed in preferences.

Please confirm if this can be scheduled for inclusion or if further clarification is needed from the customer.



 Comments   
Comment by Wajdi Jomaa [ 29/Sep/25 ]

The feature is now implemented in NEP, now patch need 3.7.1.695. 

Comment by Abir Messaikeh [ 29/Dec/25 ]

Awaiting to apply on PROD

Comment by Daljeet Singh Virdi [ 27/Jan/26 ]

Patch has been deployed on prod, waiting customer to provide closer.

Comment by Daljeet Singh Virdi [ 12/Feb/26 ]

Customer provide closure

Generated at Fri Apr 17 09:19:16 EEST 2026 using JIRA 6.1.4#6159-sha1:44eaedef2e4a625c6c7183698b2468d4719c20dc.