[LS-536] OT | Network Element DB view file preparation for AgileOps Created: 01/Aug/25  Updated: 04/Nov/25  Due: 06/Aug/25  Resolved: 09/Sep/25

Status: Closed
Project: L3 Support
Component/s: NEP
Affects Version/s: None
Fix Version/s: None

Type: CR Priority: Normal
Reporter: Aurobinda Panda Assignee: Aurobinda Panda
Resolution: Fixed Votes: 0
Labels: MS_OT
Σ Remaining Estimate: 0 minutes Remaining Estimate: 0 minutes
Σ Time Spent: 2 days, 5 hours, 30 minutes Time Spent: 2 days, 5 hours, 30 minutes
Σ Original Estimate: Not Specified Original Estimate: Not Specified

Attachments: Text File 20250901_NE_ELEMENT_VIEW.txt     Text File 20250901_SRAN_BS_VIEW.txt     Microsoft Excel Global Report SRAN_28-07.xlsx     Microsoft Excel NE Report_28-07.xlsx     Microsoft Word Network Element DB View.docx    
Issue Links:
Blocks
is blocked by LS-769 Adding EMS Details to NE DB View Desi... Cancelled
is blocked by LS-770 Adding EMS Details to NE DB View : Te... Cancelled
is blocked by LS-751 Adding EMS Details to NE DB View Closed
Relates
relates to LS-769 Adding EMS Details to NE DB View Desi... Cancelled
relates to LS-770 Adding EMS Details to NE DB View : Te... Cancelled
relates to LS-751 Adding EMS Details to NE DB View Closed
Sub-Tasks:
Key
Summary
Type
Status
Assignee
LS-614 OT | Network Element DB view file pre... Technical task Cancelled Khaled Khalil  
Customer:
OMAN-Tel
Planned Start:
Planned End:
REQUESTER: EXTERNAL
Actual Start:
Date of Baselining:

 Description   

it is required to collect different attributes from Site component report and prepare a Network Element Report DB view report & Global SRAN-BSs Report.
This file will be shared with OT team under agile Ops.



 Comments   
Comment by Marwan Kanaan [ 01/Sep/25 ]

Dear @Aurobinda Panda,

kindly know that the views are completed.

scripts attatched

Best Regards,
Marwan Kanaan I Software Developer

Comment by Aurobinda Panda [ 09/Sep/25 ]

Dear team,
As checked, the output files are correct. But it is found that the separate SRANBS View file contains the role nodes are available in network View report.
So it is not required to share separate SranBS view file.

Comment by Khaled Khalil [ 10/Sep/25 ]

The time spent on this CR is 2 days (Nouha 1 day and Marwan 1 day)