[LS-728] Date Is Not Updating In NEP In Report_Huawei RAN Created: 17/Oct/25  Updated: 27/Oct/25  Due: 12/Nov/25  Resolved: 24/Oct/25

Status: Closed
Project: L3 Support
Component/s: NEP
Affects Version/s: None
Fix Version/s: None

Type: Bug Priority: Normal
Reporter: Indrasan Yadav Assignee: Indrasan Yadav
Resolution: Fixed Votes: 0
Labels: AI_All_incidents, Huawei_RAN_OO
Remaining Estimate: 0 minutes
Time Spent: 1 day, 3 hours
Original Estimate: Not Specified

Attachments: PNG File Error report_17-10-2025.png     PNG File Inventory report.png     PNG File Old Error Report.png     PNG File Screenshot 2025-10-20 100544.png     PNG File Screenshot 2025-10-20 100727.png     PNG File cabinet report.png     PNG File eNodeB report_where other node is getting update.png     PNG File enodeB Report for nodes_date not updating.png     File ranooredoo 1.rar     File server logs.rar    
Customer:
Ooreedo Tunisia
Planned Start:
Planned End:
Rejected By: Marwan Kanaan
Actual Start:
Date of Baselining:

 Description   

Dear @Khaled Khalil,

Could you please assign an NEP DEV resource to investigate and fix the issue described below:

XML File: 2025-09-26-05.01.22_Ooredoo (Attached on JIRA)
Import Date: 17-10-2025
Platform: .102
Server Logs: (Attached on JIRA)

The date field is not updating in certain reports for some cases.
For reference, I have shared an example below.

Please note: The date should be updated for all data across all reports imported into NEP based on the XML input.
If the data is missing in the XML itself, it is expected not to update — this is not considered an issue.

Example:

Cabinet Report:

Snap attached

Inventory report:

Snap attached

Thank you
Indrasan



 Comments   
Comment by Marwan Kanaan [ 20/Oct/25 ]

Dear @Indrasan Yadav,

Kindly note that I was able to import the same data locally without any issue. Therefore, I connected to the actual version to check and found the following:

ss

ss

Comment by Indrasan Yadav [ 22/Oct/25 ]

Dear @Khaled Khalil,

Could you please assign a NEP DEV resource to check below described issue:

Still, I can see the date is not updated in below report for only 4 nodes:

eNodeB Report: Date is not updating for below given 4 nodes.

SS attached-1

SS attached-2

And the related error is like below which is related to 4G cell but all 4G cells are importing in NEP as per XML:

SS attached

This error was not appearing earlier when I checked in error report, please find below snap where the same error was missing.

SS attached

Thank you
Indrasan

Comment by Indrasan Yadav [ 24/Oct/25 ]

Dear @Indrasan Yadav,

Kindly note that the issue for the four eNodeBs that were not updating has been resolved.
Please find the solution included in patch No. 3.7.0.1370.
Best Regards,
Marwan Kanaan I Software Developer

Comment by Indrasan Yadav [ 24/Oct/25 ]

After deployed latest patch, Imported same XML & now issue is fixed.

Generated at Wed Apr 15 14:30:54 EEST 2026 using JIRA 6.1.4#6159-sha1:44eaedef2e4a625c6c7183698b2468d4719c20dc.