[OT-7] Huawei-RAN_FRS_Preparation Created: 05/May/25 Updated: 21/Jan/26 Due: 12/May/25 Resolved: 21/Jan/26 |
|
| Status: | Closed |
| Project: | Ooredoo Tunisia |
| Component/s: | None |
| Affects Version/s: | None |
| Fix Version/s: | None |
| Type: | Task | Priority: | Normal |
| Reporter: | Indrasan Yadav | Assignee: | Indrasan Yadav |
| Resolution: | Done | Votes: | 0 |
| Labels: | AI_All_incidents, Huawei_RAN_OO | ||
| Remaining Estimate: | 0 minutes | ||
| Time Spent: | 4 days, 7 hours | ||
| Original Estimate: | Not Specified | ||
| Attachments: |
|
| Customer: |
Ooreedo Tunisia
|
| Planned Start: | |
| Planned End: | |
| Actual Start: | |
| Actual End: | |
| Date of Baselining: |
| Description |
|
Need to prepare FRS for Huawei_RAN. |
| Comments |
| Comment by Bassem Sabbagh [ 06/May/25 ] |
|
there is no consolidated FRS to be considered as reference, The FRS should be amended with many updates. to be delivered on 9-5-2025 |
| Comment by Indrasan Yadav [ 12/May/25 ] |
|
FRS preparation done for physical & logical inventory both which is attached here. Note: Might be some amendment needed when we will get all full dump of Huawei from Ooredoo Tunisia. |
| Comment by Bassem Sabbagh [ 12/May/25 ] |
|
Assigned to Jharna to define the WL |
| Comment by Indrasan Yadav [ 12/May/25 ] |
|
Now, it is assigning to @Jharna as suggested by @Bassem, as she will start work on this. |
| Comment by Jharna Thakur [ 13/May/25 ] |
|
After a discussion with Indrasan Yadav, it was observed that the dumps are approximately similar to those of the Omantel Huawei RAN Connector. By using the Omantel Huawei RAN Connector to generate XML from the sample dumps, we were able to generate an XML file after making some initial adjustments to prevent null pointer exceptions. |
| Comment by Bassem Sabbagh [ 13/May/25 ] |
|
Jharna to define the WL to add the radio Antenna and fix the csv columns issues |
| Comment by Jharna Thakur [ 13/May/25 ] |
|
WL-2.5 days (to add the radio Antenna and fix the csv columns issues) |
| Comment by Bassem Sabbagh [ 14/May/25 ] |
|
a separate jira should be created for this task "Huawei RAN connector creation / update" then to be assigned to Jharna |
| Comment by Bassem Sabbagh [ 14/May/25 ] |
|
the closure is pending the customer to share samples for other nodes types for confirmation |
| Comment by Indrasan Yadav [ 21/Jan/26 ] |
|
We have already added the issue related to receiving all physical dumps while only sample logical dumps are received in the ACE Tracker. Therefore, we are closing this JIRA, as it was created only for FRS preparation, and the required FRS activity has now been completed. |