[ZKU-26] Nokia MW _License Connector development,Analyze the attached dump and upload the FRS Created: 14/Mar/24  Updated: 04/Jun/24  Due: 19/Mar/24

Status: Done
Project: Zain KSA upgradation
Component/s: None
Affects Version/s: None
Fix Version/s: None

Type: Task Priority: Urgent
Reporter: Navneet Kaur Assignee: Ahad Siddiqui
Resolution: Unresolved Votes: 0
Labels: AI_All_incidents
Remaining Estimate: 0 minutes
Time Spent: 1 week, 6 hours
Original Estimate: Not Specified

Attachments: Microsoft Word License Management Nokia_FRS(IDU)_09-04-2024_KSA.docx     File Nokia Wavence license.csv     File Site DetailsKSA.csv    
Customer:
Zain 2.X
Planned Start:
Planned End:
Complexity: Low
Severity: Blocker
Product: NEP
Classification: BUG
REQUESTER: INTERNAL
Actual Start:
Date of Baselining:

 Comments   
Comment by Bassem Sabbagh [ 14/Mar/24 ]

Please to define to WL to prepare the FRS after analyzing the dump to parse the license - New connector
Should be analyzed by next week

Comment by Ahad Siddiqui [ 18/Mar/24 ]

Analysis to be done by 21-03-2024

Comment by Bassem Sabbagh [ 22/Mar/24 ]

Wl = 0.5 mdays

Comment by Shamim Ahmed [ 26/Mar/24 ]

Dumps validation to be done on 26-3

Comment by Shamim Ahmed [ 27/Mar/24 ]

Dumps are ok but had to validate it with existing inventory and dumps

Comment by Shamim Ahmed [ 28/Mar/24 ]

After validation Total LIcense Node=5242,matched node=5188.Node NA=54.
Will intiate FRS preparation,WL= 2 days,parallely asking support for this 54 nodes.

Comment by Shamim Ahmed [ 28/Mar/24 ]

FRS preparation to be started from next week

Comment by Bassem Sabbagh [ 02/Apr/24 ]

delayed due to dumps gap analysis shared by OT

Comment by Bassem Sabbagh [ 05/Apr/24 ]

to be resumed on 8-4-2024

Comment by Bassem Sabbagh [ 08/Apr/24 ]

FRS to be created by 9-4-2024

Comment by Bassem Sabbagh [ 09/Apr/24 ]

FRS to be shared by 9-4-2024 EOD then to validated by Ahad

Comment by Shamim Ahmed [ 09/Apr/24 ]

Please find attached FRS

Comment by Ahad Siddiqui [ 15/Apr/24 ]

will Validate by 15-04 eod

Comment by Ahad Siddiqui [ 15/Apr/24 ]

Reviewed

@Bassem : PLease assign it to AI DEV

Comment by Bassem Sabbagh [ 16/Apr/24 ]

Assigned to sandya to define the Wl

Comment by Bassem Sabbagh [ 17/Apr/24 ]

to be discussed with Ahad and sandya to define the WL on 17-4

Comment by Sandya Sharma [ 17/Apr/24 ]

WL is 3 day.

Comment by Bassem Sabbagh [ 22/Apr/24 ]

to be started on 1-5 and delivered on 3-5

Comment by Sandya Sharma [ 03/May/24 ]

XML shared.

Comment by Ahad Siddiqui [ 06/May/24 ]

As discussed model is missing , please include and reshare.

Comment by Sandya Sharma [ 06/May/24 ]

XML shared.

Comment by Ahad Siddiqui [ 07/May/24 ]

import and valiadtion will be completed by 08-05

Comment by Ahad Siddiqui [ 09/May/24 ]

delayed due to OT demo and other import on ZKSA test platform , will complete on 09-05

Comment by Ahad Siddiqui [ 13/May/24 ]

Node type field was missing in the nelicense which Sandya had had fixed , import to be done on 13-05

Comment by Ahad Siddiqui [ 14/May/24 ]

import done , there is small gap in license count in NEP and XML.
Will check based on other priorities and close by 15-05

Comment by Ahad Siddiqui [ 15/May/24 ]

data succesfully loaded , JIRA can be closed.