Details

    • Customer:
      Ooreedo Tunisia

      Description

      Vendor/Manufacturer is missing in below report:

      1- Role2G
      2- Role4G
      3- Radio Antenna Report
      4- IP/VLAN/Sub Interface/Loopback Interface
      5- Additional Information either in front or inside report

        Activity

        Indrasan Yadav logged work - 08/Jul/25 12:00 AM
        • Time Spent:
          30 minutes
           

          Found this issue & raised to NEP DEV.

        Indrasan Yadav made changes -
        Field Original Value New Value
        Gantt Options Milestone (set to milestone: having a due date but zero effort)
        Planned Start 2025-07-14 24:00 (milestone: set planned start date to due date)
        Planned End 2025-07-14 24:00 (milestone: set planned end date to due date)
        Indrasan Yadav made changes -
        Attachment addinfo snap front view.png [ 112801 ]
        Attachment Addinfo snap.png [ 112802 ]
        Indrasan Yadav made changes -
        Remaining Estimate 0 minutes [ 0 ]
        Time Spent 30 minutes [ 1800 ]
        Worklog Id 271407 [ 271407 ]
        Indrasan Yadav made changes -
        Baseline Start 2025-07-14 24:00 (set baseline based of initial work logging)
        Baseline End 2025-07-14 24:00 (set baseline based of initial work logging)
        Indrasan Yadav logged work - 14/Jul/25 12:00 AM
        • Time Spent:
          30 minutes
           

          Take an overview & send an email to NEP DEV team to update on same.

        Hide
        Indrasan Yadav added a comment -

        Dear @Khaled Khalil,

        Any update on this?

        Thank you
        Indrasan

        Show
        Indrasan Yadav added a comment - Dear @Khaled Khalil, Any update on this? Thank you Indrasan
        Indrasan Yadav made changes -
        Time Spent 30 minutes [ 1800 ] 1 hour [ 3600 ]
        Worklog Id 271809 [ 271809 ]
        Nouha Mhadhbi made changes -
        Assignee Khaled Khalil [ kkhalil ] Nouha Mhadhbi [ nmhadhbi ]
        Hassan Abdine made changes -
        Issue Type Bug [ 1 ] CR [ 10900 ]
        Workflow Mobinets_Dev_BugWF_J4.4 [ 188802 ] Mobinets_Dev_WF_J4.4 [ 190713 ]
        Status Open Bug [ 10108 ] Opened [ 1 ]
        Khaled Khalil made changes -
        Component/s NEP [ 16200 ]
        Khaled Khalil made changes -
        Assignee Nouha Mhadhbi [ nmhadhbi ] Khaled Khalil [ kkhalil ]
        Indrasan Yadav logged work - 16/Sep/25 12:00 AM
        • Time Spent:
          30 minutes
           

          Checked in report still issue is same so send a reminder to NEP DEV.

        Hide
        Indrasan Yadav added a comment -

        Dear Khaled Khalil,

        Could you please update on this?

        Thank you
        Indrasan

        Show
        Indrasan Yadav added a comment - Dear Khaled Khalil , Could you please update on this? Thank you Indrasan
        Indrasan Yadav made changes -
        Time Spent 1 hour [ 3600 ] 1 hour, 30 minutes [ 5400 ]
        Worklog Id 277564 [ 277564 ]
        Hide
        Indrasan Yadav added a comment -

        From: Khaled Khalil <Khaled.Khalil@mobinets.com>
        Sent: Tuesday, September 16, 2025 5:21 PM
        To: Indrasan Yadav <Indrasan.Yadav@nuiva.com>; Khaled Khalil <Khaled.Khalil@nuiva.com>; Hassan Abdine <Hassan.Abdine@nuiva.com>
        Cc: Bassem Sabbagh <bassem.sabbagh@mobinets.com>
        Subject: Re: Vendor Is Missing In Report || LS-495 ||

        ++looping @Hassan Abdine kindly advise if we will implement this request

        Show
        Indrasan Yadav added a comment - From: Khaled Khalil <Khaled.Khalil@mobinets.com> Sent: Tuesday, September 16, 2025 5:21 PM To: Indrasan Yadav <Indrasan.Yadav@nuiva.com>; Khaled Khalil <Khaled.Khalil@nuiva.com>; Hassan Abdine <Hassan.Abdine@nuiva.com> Cc: Bassem Sabbagh <bassem.sabbagh@mobinets.com> Subject: Re: Vendor Is Missing In Report || LS-495 || ++looping @Hassan Abdine kindly advise if we will implement this request
        Hide
        Indrasan Yadav added a comment -

        From: Hassan Abdine <Hassan.Abdine@nuiva.com>
        Sent: Wednesday, September 17, 2025 9:02 AM
        To: Khaled Khalil <Khaled.Khalil@mobinets.com>; Indrasan Yadav <Indrasan.Yadav@nuiva.com>; Khaled Khalil <Khaled.Khalil@nuiva.com>
        Cc: Bassem Sabbagh <bassem.sabbagh@mobinets.com>
        Subject: Re: Vendor Is Missing In Report || LS-495 ||

        What is the need of addition the vendor to the below reports ?

        Thank you,
        Hassan

        Show
        Indrasan Yadav added a comment - From: Hassan Abdine <Hassan.Abdine@nuiva.com> Sent: Wednesday, September 17, 2025 9:02 AM To: Khaled Khalil <Khaled.Khalil@mobinets.com>; Indrasan Yadav <Indrasan.Yadav@nuiva.com>; Khaled Khalil <Khaled.Khalil@nuiva.com> Cc: Bassem Sabbagh <bassem.sabbagh@mobinets.com> Subject: Re: Vendor Is Missing In Report || LS-495 || What is the need of addition the vendor to the below reports ? Thank you, Hassan
        Hide
        Indrasan Yadav added a comment -

        Salam,

        It is facilitating and speed up the validation of Data in NEP ..

        Thanks
        Bassem

        Show
        Indrasan Yadav added a comment - Salam, It is facilitating and speed up the validation of Data in NEP .. Thanks Bassem
        Hide
        Indrasan Yadav added a comment -

        Dear All,

        Kindly update on this.

        Thank you
        Indrasan

        Show
        Indrasan Yadav added a comment - Dear All, Kindly update on this. Thank you Indrasan
        Indrasan Yadav logged work - 22/Dec/25 12:00 AM
        • Time Spent:
          1 hour
           

          First check all pending JIRA during tracker (Ace-Tracker) update which was shared by @Bassem and discussed with @Hassan for this over teams that should I close this or we can fix for at least point 1/2/3, he confirmed we can fix for point 1/2/3. shared an email for same to @Bassem.

        Hide
        Indrasan Yadav added a comment -

        Dear @Bassem Sabbagh,

        As confirmed with @Hassan Abdine, we can update the vendor for the following tables for now and ignore the others:

        1. Role2G
        2. Role4G
        3. Radio Antenna Report

        Kindly coordinate with the NEP DEV team to review and fix this on a priority basis.

        Thank you.

        Best regards,
        Indrasan

        Show
        Indrasan Yadav added a comment - Dear @Bassem Sabbagh, As confirmed with @Hassan Abdine, we can update the vendor for the following tables for now and ignore the others: 1. Role2G 2. Role4G 3. Radio Antenna Report Kindly coordinate with the NEP DEV team to review and fix this on a priority basis. Thank you. Best regards, Indrasan
        Indrasan Yadav made changes -
        Time Spent 1 hour, 30 minutes [ 5400 ] 2 hours, 30 minutes [ 9000 ]
        Worklog Id 286632 [ 286632 ]
        Indrasan Yadav logged work - 31/Dec/25 12:00 AM
        • Time Spent:
          2 hours
           

          Discuss with Bassem about the pending issue & explain the same to Marwan. and updated the ACE tracker for all pending/open issues and shared the same sheet to @Bassem.

        Marwan Kanaan logged work - 31/Dec/25 12:00 AM
        • Time Spent:
          3 hours
           

          added the vendor column for the requested reports

        Marwan Kanaan made changes -
        Assignee Khaled Khalil [ kkhalil ] Marwan Kanaan [ mkanaan ]
        Indrasan Yadav made changes -
        Time Spent 2 hours, 30 minutes [ 9000 ] 4 hours, 30 minutes [ 16200 ]
        Worklog Id 287837 [ 287837 ]
        Marwan Kanaan made changes -
        Time Spent 4 hours, 30 minutes [ 16200 ] 7 hours, 30 minutes [ 27000 ]
        Worklog Id 287841 [ 287841 ]
        Khaled Khalil made changes -
        Status Opened [ 1 ] Pending Requirements [ 10300 ]
        Khaled Khalil made changes -
        Status Pending Requirements [ 10300 ] Pending Design Session [ 10112 ]
        Assignee Marwan Kanaan [ mkanaan ] Khaled Khalil [ kkhalil ]
        Khaled Khalil made changes -
        Status Pending Design Session [ 10112 ] Dev Scheduled [ 10014 ]
        Assignee Khaled Khalil [ kkhalil ] Marwan Kanaan [ mkanaan ]
        Khaled Khalil made changes -
        Status Dev Scheduled [ 10014 ] Implementation in progress [ 10016 ]
        Assignee Marwan Kanaan [ mkanaan ] Khaled Khalil [ kkhalil ]
        Hide
        Marwan Kanaan added a comment -

        Dear @Indrasan Yadav,

        Kindly note that the vendor column has now been added to the requested reports.
        Additionally, the duplicated column in the SRAN-BS report has been removed.
        These updates are included in Patch NB: 3.7.0.1400.

        Best Regards,
        Marwan Kanaan I Software Developer

        Show
        Marwan Kanaan added a comment - Dear @Indrasan Yadav, Kindly note that the vendor column has now been added to the requested reports. Additionally, the duplicated column in the SRAN-BS report has been removed. These updates are included in Patch NB: 3.7.0.1400. Best Regards, Marwan Kanaan I Software Developer
        Marwan Kanaan made changes -
        Status Implementation in progress [ 10016 ] To Be Released [ 10400 ]
        Khaled Khalil made changes -
        Status To Be Released [ 10400 ] Ready for QA [ 10023 ]
        Assignee Khaled Khalil [ kkhalil ] Indrasan Yadav [ iyadav ]
        Indrasan Yadav logged work - 05/Jan/26 12:00 AM - edited
        • Time Spent:
          1 hour
           

          Validated the data for same.

        Hide
        Indrasan Yadav added a comment -

        Dear @Marwan Kanaan,

        Thank you.

        The issue has now been fixed for the following tables after deploying the latest NEP patch.

        Role2G
        Role3G
        Role4G
        Radio Antenna

        Best regards,
        Indrasan

        Show
        Indrasan Yadav added a comment - Dear @Marwan Kanaan, Thank you. The issue has now been fixed for the following tables after deploying the latest NEP patch. Role2G Role3G Role4G Radio Antenna Best regards, Indrasan
        Indrasan Yadav made changes -
        Status Ready for QA [ 10023 ] QA In Progress [ 10015 ]
        Indrasan Yadav made changes -
        Status QA In Progress [ 10015 ] Closed [ 6 ]
        Resolution Fixed [ 1 ]
        Indrasan Yadav made changes -
        Time Spent 7 hours, 30 minutes [ 27000 ] 1 day, 1 hour, 30 minutes [ 34200 ]
        Worklog Id 288110 [ 288110 ]
        Indrasan Yadav made changes -
        Remaining Estimate 0 minutes [ 0 ] 1 hour [ 3600 ]
        Time Spent 1 day, 1 hour, 30 minutes [ 34200 ] 1 day, 30 minutes [ 30600 ]
        Worklog Id 288110 [ 288110 ]
        Transition Time In Source Status Execution Times Last Executer Last Execution Date
        Open Bug Open Bug Opened Opened
        28d 4h 4m 1 Hassan Abdine 05/Aug/25 11:05 AM
        Opened Opened Pending Requirements Pending Requirements
        148d 2h 27m 1 Khaled Khalil 31/Dec/25 12:32 PM
        Pending Requirements Pending Requirements Pending Design Session Pending Design Session
        10s 1 Khaled Khalil 31/Dec/25 12:33 PM
        Pending Design Session Pending Design Session Dev Scheduled Dev Scheduled
        19s 1 Khaled Khalil 31/Dec/25 12:33 PM
        Dev Scheduled Dev Scheduled Implementation in progress Implementation in progress
        5s 1 Khaled Khalil 31/Dec/25 12:33 PM
        Implementation in progress Implementation in progress To Be Released To Be Released
        1m 30s 1 Marwan Kanaan 31/Dec/25 12:34 PM
        To Be Released To Be Released Ready for QA Ready for QA
        24m 39s 1 Khaled Khalil 31/Dec/25 12:59 PM
        Ready for QA Ready for QA QA In Progress QA In Progress
        4d 16h 57m 1 Indrasan Yadav 05/Jan/26 5:57 AM
        QA In Progress QA In Progress Closed Closed
        21s 1 Indrasan Yadav 05/Jan/26 5:57 AM
        Subversion JIRA

        Links Hierarchy

         Documentation

        Invalid license: EXPIRED

          People

          • Assignee:
            Indrasan Yadav
            Reporter:
            Indrasan Yadav
          • Votes:
            0 Vote for this issue
            Watchers:
            2 Start watching this issue

            Dates

            • Due:
              Created:
              Updated:
              Resolved:
              Planned Start:
              Planned End:
              Actual Start:
              Date of Baselining:

              Time Tracking

              Estimated:
              Original Estimate - Not Specified
              Not Specified
              Remaining:
              Time Spent - 1 day, 30 minutes Remaining Estimate - 1 hour
              1h
              Logged:
              Time Spent - 1 day, 30 minutes Remaining Estimate - 1 hour
              1d 30m

                Drag and Drop