Details
-
Type:
Task
-
Status:
Done
(View Workflow)
-
Priority:
Normal
-
Resolution: Unresolved
-
Labels:
-
Customer:Zain KSA 3.X
Description
Click to add description
Attachments
Issue Links
- blocks
-
ZKU-94
Huawei RAN_Dumps , XML and NEP data Validation
-
Activity
|
Links Hierarchy |
Documentation
|
| Transition | Time In Source Status | Execution Times | Last Executer | Last Execution Date | |||||
|---|---|---|---|---|---|---|---|---|---|
|
2d 21h 34m | 1 | Mustapha Al-Hage | 05/Dec/24 1:06 PM | |||||
|
5s | 1 | Mustapha Al-Hage | 05/Dec/24 1:06 PM | |||||
|
17h 23m | 1 | Indrasan Yadav | 06/Dec/24 6:30 AM | |||||
|
7d 1h 48m | 1 | Indrasan Yadav | 13/Dec/24 8:18 AM |
| Status | To Do [ 10001 ] | Done [ 10000 ] |
| Assignee | Sandya Sharma [ ssharma ] | Indrasan Yadav [ iyadav ] |
| Assignee | Indrasan Yadav [ iyadav ] | Sandya Sharma [ ssharma ] |
| Assignee | Sandya Sharma [ ssharma ] | Indrasan Yadav [ iyadav ] |
| Assignee | Indrasan Yadav [ iyadav ] | Sandya Sharma [ ssharma ] |
| Status | Done [ 10000 ] | To Do [ 10001 ] |
| Time Spent | 4 hours [ 14400 ] | 1 day [ 28800 ] |
| Worklog Id | 257969 [ 257969 ] |
| Baseline Start | 2024-12-09 24:00 (set baseline based of initial work logging) | |
| Baseline End | 2024-12-09 24:00 (set baseline based of initial work logging) |
| Remaining Estimate | 0 minutes [ 0 ] | |
| Time Spent | 4 hours [ 14400 ] | |
| Worklog Id | 257967 [ 257967 ] |
| Assignee | Mustapha Al-Hage [ malhage ] | Indrasan Yadav [ iyadav ] |
| Status | In Progress [ 3 ] | Done [ 10000 ] |
| Status | To Do [ 10001 ] | In Progress [ 3 ] |
| Attachment | XML_NODECABINETS_NODEID_COLUMN.png [ 103370 ] |
| Attachment | XML_NODECABINETS_MISSING_NODEID_COLUMN.png [ 103369 ] |
| Summary | Cabinet And Shelf Serial Number Is Not Importing In NEP While Available In XML_Huawei | Cabinet And Shelf Serial Number Is Not Importing In NEP While Available In XML_Huawei RAN |
| Assignee | Diana Hamdouche [ dhamdouche ] | Mustapha Al-Hage [ malhage ] |
| Assignee | Khaled Khalil [ kkhalil ] | Diana Hamdouche [ dhamdouche ] |
| Assignee | Indrasan Yadav [ iyadav ] | Khaled Khalil [ kkhalil ] |
| Summary | Serial Number Not Imported Of Cabinet And Shelf In NEP While Available In XML_Huawei | Cabinet And Shelf Serial Number Is Not Importing In NEP While Available In XML_Huawei |
| Field | Original Value | New Value |
|---|---|---|
| Gantt Options | Milestone (set to milestone: having a due date but zero effort) | |
| Planned Start | 2024-12-09 24:00 (milestone: set planned start date to due date) | |
| Planned End | 2024-12-09 24:00 (milestone: set planned end date to due date) |
Documentation
We are now closing this child JIRA as it pertains to an individual issue.
As suggested by @Ahad, all code commit JIRAs will be covered under the parent JIRA.