        Indrasan Yadav logged work - 08/Jan/25 12:00 AM
        • Time Spent:
          2 hours, 30 minutes
           

          Started working on the preparation of the Huawei FRS.

        Indrasan Yadav logged work - 13/Jan/25 12:00 AM - edited
        • Time Spent:
          3 hours, 30 minutes
           

          Worked to prepare FRS for licenses.

        Indrasan Yadav logged work - 17/Jan/25 12:00 AM
        • Time Spent:
          1 day
           

          Worked on to prepare FRS for Huawei RAN

        Indrasan Yadav logged work - 20/Jan/25 12:00 AM
        • Time Spent:
          6 hours
           

          Worked on to prepare FRS for Huawei RAN

        Indrasan Yadav logged work - 21/Jan/25 12:00 AM - edited
        • Time Spent:
          7 hours, 30 minutes
           

          Worked on to prepare FRS for Huawei RAN

          People

          • Assignee:
            Indrasan Yadav
            Reporter:
            Indrasan Yadav
          • Votes:
            0 Vote for this issue
            Watchers:
            2 Start watching this issue

            Dates

            • Due:
              Created:
              Updated:
              Planned Start:
              Planned End:
              Actual Start:
              Date of Baselining:

              Time Tracking

              Estimated:
              Original Estimate - Not Specified
              Not Specified
              Remaining:
              Time Spent - 3 days, 3 hours, 30 minutes Remaining Estimate - 30 minutes
              30m
              Logged:
              Time Spent - 3 days, 3 hours, 30 minutes Remaining Estimate - 30 minutes
              3d 3h 30m