Details
-
Type:
CR
-
Status:
Need More Info
(View Workflow)
-
Resolution: Unresolved
-
Component/s: SRD
-
Customer:OMAN-Tel
-
Reason:Missing requirements
-
Severity:Minor
-
Classification:CR
Description
Current Scenarios: We need to start over request to change from MW and GE to VSAT
New planed scenarios: After getting MW and GE solution need to have option like GPON scenario “PROCEED_WITH_GPON”. Please find steps and you may change to improve it:
1- We suggest after getting MW and GE solution to back TAS team as PROCEED_WITH_MW_AND_GE
2- If we approved, then will come to TAS as SOLUTION_ACCEPTANCE
3- If we reject, should back to us to change service resources to select VSAT design.
4- After getting VSAT design then back to TAS for SOLUTION_ACCEPTANCE
Attachments
Activity
| Field | Original Value | New Value |
|---|---|---|
| Gantt Options | Milestone (set to milestone: having a due date but zero effort) | |
| Planned Start | 2024-09-13 24:00 (milestone: set planned start date to due date) | |
| Planned End | 2024-09-13 24:00 (milestone: set planned end date to due date) |
| Assignee | Bassem Sabbagh [ bsabbagh ] | Khaled Khalil [ kkhalil ] |
| Status | Opened [ 1 ] | Registered [ 10304 ] |
| Status | Registered [ 10304 ] | Customer Contacted [ 10305 ] |
| Status | Customer Contacted [ 10305 ] | L1 In Progress [ 10200 ] |
| Status | L1 In Progress [ 10200 ] | L3 In Progress [ 10202 ] |
| Classification | CR [ 13201 ] |
| Assignee | Khaled Khalil [ kkhalil ] | Mohamad Kalawoun [ mkalawoun ] |
| Attachment | MOB-6953-Tasks.docx [ 102037 ] |
| Project | Mobinets_Support [ 10405 ] | L3 Support [ 14300 ] |
| Key | MOB-6953 | LS-36 |
| Workflow | Support_WF_ABIR [ 177718 ] | Mobinets_Dev_WF_J4.4 [ 179203 ] |
| Status | L3 In Progress [ 10202 ] | Implementation in progress [ 10016 ] |
| Reporter | Salem Dannawi [ sdannawi ] | Abir Messaikeh [ amessaikeh ] |
| Issue Type | Feature [ 10101 ] | CR [ 10900 ] |
| Assignee | Mohamad Kalawoun [ mkalawoun ] |
| Reporter | Abir Messaikeh [ amessaikeh ] | Salem Dannawi [ sdannawi ] |
| Assignee | Mohamad Kalawoun [ mkalawoun ] |
| Status | Implementation in progress [ 10016 ] | Dev Paused [ 10017 ] |
| Status | Dev Paused [ 10017 ] | Implementation in progress [ 10016 ] |
| Status | Implementation in progress [ 10016 ] | Pending Requirements [ 10300 ] |
| Status | Pending Requirements [ 10300 ] | Pending Design Session [ 10112 ] |
| Assignee | Mohamad Kalawoun [ mkalawoun ] | Khaled Khalil [ kkhalil ] |
| Attachment | SRD_re-initialize_option.pdf [ 103659 ] | |
| Attachment | SRD_re-initialize_option.docx [ 103660 ] |
| Component/s | SRD [ 16202 ] |
| Status | Pending Design Session [ 10112 ] | Pending Requirements [ 10300 ] |
| Reason | Missing requirements [ 10401 ] |
| Status | Pending Requirements [ 10300 ] | Need More Info [ 10011 ] |
| Transition | Time In Source Status | Execution Times | Last Executer | Last Execution Date | |||||
|---|---|---|---|---|---|---|---|---|---|
|
11s | 1 | Salem Dannawi | 03/Sep/24 5:47 AM | |||||
|
3s | 1 | Salem Dannawi | 03/Sep/24 5:47 AM | |||||
|
2s | 1 | Salem Dannawi | 03/Sep/24 5:48 AM | |||||
|
3s | 1 | Salem Dannawi | 03/Sep/24 5:48 AM | |||||
|
103d 8h 39m | 1 | Hassan Abdine | 15/Dec/24 1:27 PM | |||||
|
3h 13m | 1 | Khaled Khalil | 15/Dec/24 4:41 PM | |||||
|
2d 18h 18m | 1 | Hassan Abdine | 18/Dec/24 10:59 AM | |||||
|
9s | 1 | Hassan Abdine | 18/Dec/24 10:59 AM | |||||
|
17s | 1 | Hassan Abdine | 18/Dec/24 10:59 AM | |||||
|
240d 8m | 1 | Abir Messaikeh | 15/Aug/25 12:08 PM | |||||
|
7s | 1 | Abir Messaikeh | 15/Aug/25 12:08 PM |
|
Links Hierarchy |
Documentation
|
Documentation