Details

    • Customer:
      OMAN-Tel

      Description

      the issue here in the requests on production,
      after completing the proceed with gpon task,
      the request hang on design in progress and the solution acceptance task is not created,
      I have created the same request on staging platform .179 and it's working fine on staging,( request 172217 )
      I have compared the date of processes all is same in prod and staging.
      Please advise,
      logs will be shared once received from integration

        Activity

        Hide
        added a comment -

        In the production logs, I found that the issue was internal to Flowable. The process was blocking the execution from completing the human task PROCEED_WITH_GPON.
        I have modified the design while respecting the mentioned business rules and scenario. After testing on the staging environment, the issue does not exist.
        Please test on the production platform after deploying the updated process version
        Kind regards,

        Show
        added a comment - In the production logs, I found that the issue was internal to Flowable. The process was blocking the execution from completing the human task PROCEED_WITH_GPON. I have modified the design while respecting the mentioned business rules and scenario. After testing on the staging environment, the issue does not exist. Please test on the production platform after deploying the updated process version Kind regards,

          People

          • Assignee:
            Salem Dannawi
            Reporter:
            Salem Dannawi
          • Votes:
            0 Vote for this issue
            Watchers:
            1 Start watching this issue

            Dates

            • Due:
              Created:
              Updated:
              Resolved:
              Planned Start:
              Planned End:
              Actual Start:
              Date of Baselining:

              Time Tracking

              Estimated:
              Original Estimate - Not Specified
              Not Specified
              Remaining:
              Remaining Estimate - 0 minutes
              0m
              Logged:
              Time Spent - 1 day, 1 hour
              1d 1h