Details

    • Type: Bug Bug
    • Status: Closed Closed (View Workflow)
    • Priority: Normal Normal
    • Resolution: Fixed
    • Component/s: NEP
    • Labels:
      None Labels
    • Customer:
      OMAN-Tel
    • Product:
      NEP

      Description

      End user is updating the SLA Cong from the service account report and team are now asking to be reflected automatically to the node and to be matched with CE Custom report as well based on Service account.

        Activity

        Abir Messaikeh made changes -
        Status QA In Progress [ 10015 ] Closed [ 6 ]
        Resolution Fixed [ 1 ]
        Abir Messaikeh made changes -
        Status Ready for QA [ 10023 ] QA In Progress [ 10015 ]
        Assignee Khaled M Ayoubi [ khaled.ayoubi ] Abir Messaikeh [ amessaikeh ]
        Khaled Khalil made changes -
        Status To Be Released [ 10400 ] Ready for QA [ 10023 ]
        Assignee Marwan Kanaan [ mkanaan ] Khaled M Ayoubi [ khaled.ayoubi ]
        Marwan Kanaan made changes -
        Time Spent 1 day [ 28800 ] 2 days [ 57600 ]
        Worklog Id 294509 [ 294509 ]
        Marwan Kanaan made changes -
        Status Implementation in progress [ 10016 ] To Be Released [ 10400 ]
        Marwan Kanaan made changes -
        Baseline Start 2026-03-16 24:00 (set baseline based of initial work logging)
        Baseline End 2026-03-16 24:00 (set baseline based of initial work logging)
        Marwan Kanaan made changes -
        Remaining Estimate 0 minutes [ 0 ]
        Time Spent 1 day [ 28800 ]
        Worklog Id 294408 [ 294408 ]
        Abir Messaikeh made changes -
        Reporter Abdulrahman Dabboussi [ adabboussi ] Khaled M Ayoubi [ khaled.ayoubi ]
        Marwan Kanaan made changes -
        Status Dev Paused [ 10017 ] Implementation in progress [ 10016 ]
        Marwan Kanaan made changes -
        Status Implementation in progress [ 10016 ] Dev Paused [ 10017 ]
        Marwan Kanaan made changes -
        Status Dev Scheduled [ 10014 ] Implementation in progress [ 10016 ]
        Marwan Kanaan made changes -
        Status Open Bug [ 10108 ] Dev Scheduled [ 10014 ]
        Marwan Kanaan made changes -
        Assignee Khaled Khalil [ kkhalil ] Marwan Kanaan [ mkanaan ]
        Abdulrahman Dabboussi made changes -
        Field Original Value New Value
        Gantt Options Milestone (set to milestone: having a due date but zero effort)
        Planned Start 2026-03-16 24:00 (milestone: set planned start date to due date)
        Planned End 2026-03-16 24:00 (milestone: set planned end date to due date)

          People

          • Assignee:
            Abir Messaikeh
            Reporter:
            Khaled M Ayoubi
          • Votes:
            0 Vote for this issue
            Watchers:
            3 Start watching this issue

            Dates

            • Due:
              Created:
              Updated:
              Resolved:
              Planned Start:
              Planned End:
              Actual Start:
              Date of Baselining:

              Time Tracking

              Estimated:
              Original Estimate - Not Specified
              Not Specified
              Remaining:
              Remaining Estimate - 0 minutes
              0m
              Logged:
              Time Spent - 2 days
              2d