Details

    • Customer:
      Ooreedo Tunisia

      Description

      Dear @Bassem Sabbagh,

      As discussed earlier, and as per the inputs shared in the first email of this thread, for Huawei RAN we are currently using five static sheets, with the status detailed below:

      Huawei RAN – Static Sheets Status
      1. GSM_Frequency_Band
      o This will be considered as-is based on the Ooredoo dump.
      o All extra/non-applicable data has been removed.
      o I have updated the static sheet as well as the FRS and attached them to JIRA OT-139.
      2. UMTS_Frequency_Band
      o Priority: Rule-based parsing as per FRS.
      o If the value is not found via rule, the static sheet will be used as fallback.
      o The required updates have been completed and attached to JIRA OT-139.
      3. Supported_Bandwidth
      o Although this sheet was earlier considered for parsing possible bandwidths based on the value of frequency band,
      o We already have FRS rules to parse:
       Uplink channel bandwidth
       Downlink channel bandwidth
       Frequency band
      o Hence, this static sheet will be ignored, and parsing will strictly follow the FRS rules.
      4. Node_Matching
      o This sheet is updated & removed all extra data which is not applicable for Ooredoo based on available dump. (Attached on same JIRA OT-139)
      o Updated the FRS for same.
      5. HW_Matching
      o In progress.
      o Will be shared by tomorrow EOD.

      Please assign an AI-DEV resource to implement this change in Huawei RAN.

      Best regards,
      Indrasan

      1. GSM_Frequency_Band.xlsx
        10 kB
        Indrasan Yadav
      2. HW_MatchingFile.xlsx
        31 kB
        Indrasan Yadav
      3. Nodes_Matching.xls
        29 kB
        Indrasan Yadav
      4. OT_Huawei_RAN_2G_Logical & Interfaces.docx
        822 kB
        Indrasan Yadav
      5. OT_Huawei_RAN_3G_Logical & Interfaces.docx
        1.59 MB
        Indrasan Yadav
      6. OT_Huawei_RAN_4G_Logical & Interfaces_20-01-2026.docx
        382 kB
        Indrasan Yadav
      7. OT_Huawei_RAN All Nodes_Physical.docx
        1.67 MB
        Indrasan Yadav
      8. UTMS_Frequency_Band.xlsx
        10 kB
        Indrasan Yadav

        Activity

        Indrasan Yadav logged work - 11/Feb/26 12:00 AM - edited
        • Time Spent:
          2 hours
           

          Check data on NEP after imported an xml which was generated from server by integration.

        Basant Kumar logged work - 10/Feb/26 12:00 AM
        • Time Spent:
          2 hours
           

          The latest nep_ai_batch_68 has been successfully deployed.

          After deployment, I copied the required sheet into the static folder. Following this, I generated the Huawei RAN XML and CSV successfully.

        Indrasan Yadav logged work - 10/Feb/26 12:00 AM
        • Time Spent:
          5 hours
           

          Validated the same data in staging-DB.

        Indrasan Yadav logged work - 09/Feb/26 12:00 AM - edited
        • Time Spent:
          3 hours, 30 minutes
           

          Validated the updated one XML which was shared by Jharna and now issue is fixed, copy the same on server & imported the same XML. Validated the data in NEP. and shared the require related static sheet to integration to copy it on server and generated the XML/CSV output for Huawei RAN & share the same then upload the csv output on staging-DB & share the importer id.

        Jharna Thakur logged work - 06/Feb/26 12:00 AM
        • Time Spent:
          1 hour, 30 minutes
           

          working on coordinate issue

        Jharna Thakur logged work - 06/Feb/26 12:00 AM
        • Time Spent:
          3 hours, 45 minutes
           

          working on the feedback

        Indrasan Yadav logged work - 06/Feb/26 12:00 AM
        • Time Spent:
          2 hours, 30 minutes
           

          Followed up with Jharna to share the requested xml and validated it once received & again there is an issue in xml as lat-long was missing so again discussed with her & asked to fix the same..

        Indrasan Yadav logged work - 04/Feb/26 12:00 AM
        • Time Spent:
          1 day
           

          Based on error report changes in catalogue & reimport the same XML and validated the same. and there is some minor points which is raised to Jharna to fix the same and asked to share the XML with CSV Output.

        Jharna Thakur logged work - 03/Feb/26 12:00 AM
        • Time Spent:
          3 hours, 20 minutes
           

          working on feedback

        Indrasan Yadav logged work - 03/Feb/26 12:00 AM
        • Time Spent:
          7 hours
           

          Changes in catalogue based on new static sheet & then imported the xml and check error report.

        Indrasan Yadav logged work - 02/Feb/26 12:00 AM
        • Time Spent:
          7 hours
           

          XML validation of Huawei RAN which was shared by Jharna and this XML was generated with using of updated static sheet and there will be need to change in catalogue before import the xml and I have shared an email to Bassem for same.

        Jharna Thakur logged work - 30/Jan/26 12:00 AM
        • Time Spent:
          3 hours, 45 minutes
           

          working on feedback

        Indrasan Yadav logged work - 29/Jan/26 12:00 AM
        • Time Spent:
          7 hours
           

          Validated the Huawei RAN csv-output which was shared by @Jharna over teams (CSV Output was generated wit using only shared static sheet) and discussed with her to explain about issue and send an email for same.

        Jharna Thakur logged work - 28/Jan/26 12:00 AM
        • Time Spent:
          2 hours
           

          small changes regarding it

        Indrasan Yadav logged work - 28/Jan/26 12:00 AM
        • Time Spent:
          30 minutes
           

          Discussed with Jharna & taken the follows up to share the xml with using the given static sheet only.

        Indrasan Yadav logged work - 21/Jan/26 12:00 AM
        • Time Spent:
          1 day
           

          Worked on Huawei RAN static sheet for Node_Matching & HW_Matching and updated the FRS for same.

        Indrasan Yadav logged work - 20/Jan/26 12:00 AM - edited
        • Time Spent:
          5 hours
           

          Worked for Huawei RAN (Updated the static sheets & FRS as well)

        Indrasan Yadav logged work - 19/Jan/26 12:00 AM
        • Time Spent:
          1 day
           

          Worked for all using sheet in Huawei RAN & Updated the same as per current Ooredoo dump.

          People

          • Assignee:
            Indrasan Yadav
            Reporter:
            Indrasan Yadav
          • Votes:
            0 Vote for this issue
            Watchers:
            3 Start watching this issue

            Dates

            • Due:
              Created:
              Updated:
              Resolved:
              Planned Start:
              Planned End:
              Actual Start:
              Actual End:
              Date of Baselining:

              Time Tracking

              Estimated:
              Original Estimate - Not Specified
              Not Specified
              Remaining:
              Time Spent - 1 week, 4 days, 7 hours, 50 minutes Remaining Estimate - 5 hours
              5h
              Logged:
              Time Spent - 1 week, 4 days, 7 hours, 50 minutes Remaining Estimate - 5 hours
              1w 4d 7h 50m